COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
Our principal commitments as of September 30, 2026 consisted primarily of obligations under operating leases, finance leases, pension obligations, warranty liabilities, and purchase agreements. Our minimum purchase commitments as of September 30, 2026 totaled approximately $51.0 million. These amounts represent the noncancelable portions of purchase agreements or, for agreements that permit cancellation, the minimum remaining amounts payable under the applicable cancellation provisions. We expect to satisfy these minimum commitments through purchases under the agreements within the next twelve months.
Loss Contingencies:
In the ordinary course of business, the Company is regularly subject to various legal proceedings. The Company records a loss contingency accrual when a loss is both probable and reasonably estimable. As of September 30, 2026, the Company had not recorded any material loss contingency accruals related to legal proceedings. Although the Company currently believes that resolving claims against the Company, including claims where an unfavorable outcome is reasonably possible, will not have a material impact on the Company’s business, financial position, results of operations, or cash
flows, these matters are subject to inherent uncertainties and the Company’s view of these matters may change in the future.
Warranty Liabilities:
The Company provides a limited warranty to its BESS customers assuring that the BESSs are free from defects. The Company’s limited warranties are generally for a period of two or three years after the substantial completion date of the applicable project. These warranties are considered assurance-type warranties, which provide a guarantee of quality of the products. For assurance-type warranties in engineering, procurement, and construction (“EPC”) contracts, the Company records an estimate of future warranty costs over the period of construction. For assurance-type warranties in engineered equipment (“EEQ”) contracts, the Company records an estimate of future warranty costs upon the transfer of the equipment to the customer. Warranty costs are recorded as a component of cost of revenue in the Company’s condensed consolidated statements of operations and comprehensive loss.
The following table presents activity in the Company’s estimated warranty liabilities for the three and nine months ended September 30, 2026 and 2025 (amounts in thousands):
Three Months Ended September 30,Nine Months Ended September 30,
2026202520262025
Warranty liabilities, balance at beginning of period$2,030 $1,308 $467 $1,391 
Accruals for warranties issued— — 1,503 926 
Change in estimates— (582)84 (782)
Costs paid or settled(35)(110)(59)(919)
Foreign currency translation adjustment18 — 18 — 
Warranty liabilities, balance at end of period$2,013 $616 $2,013 $616 
The key inputs and assumptions used in calculating the estimated warranty liabilities are reviewed by management each reporting period. The Company may make additional adjustments to the estimated warranty liability based on a comparison of actual warranty results to expected results for significant differences or based on performance trends or other qualitative factors. If actual failure rates or replacement costs differ from our estimates in future periods, changes to these estimates may be required, resulting in increases or decreases in the estimated warranty liability, which may be material.
Letters of Credit and Bank Guarantees:
In the ordinary course of business and under certain contracts, the Company is required to post letters of credit or bank guarantees for its customers, for project performance, and for its vendors for payment guarantees. Such letters of credit or bank guarantees are generally issued by a bank or a similar financial institution. The letter of credit or bank guarantee commits the issuer to pay specified amounts to the holder of the letter of credit or bank guarantee under certain conditions. As of September 30, 2026, the Company had $18.0 million in outstanding letters of credit and $19.6 million in bank guarantees issued through the Company’s credit relationships. The Company’s outstanding letters of credit and bank guarantees are collateralized by cash classified as restricted cash on the condensed consolidated balance sheets. The Company is not aware of any material claims relating to its outstanding letters of credit or bank guarantees.
Performance and Payment Bonds:
In the ordinary course of business, Energy Vault is required by certain customers to provide performance and payment bonds for contractual commitments related to its projects. These bonds provide a guarantee that the Company will perform under the terms of a contract and that the Company will pay its subcontractors and vendors. If the Company fails to perform under a contract or to pay its subcontractors and vendors, the customer may demand that the surety make payments or provide services under the bond. The Company must reimburse the surety for expenses or outlays it incurs. As of September 30, 2026, the Company had $86.9 million in outstanding performance and payment bonds.
Other Bonds:
In the ordinary course of business, Energy Vault is required to obtain other bonds, such as for insurance and government payments. These bonds provide a guarantee that the Company will post the necessary reserves as required by banks and tax or licensing authorities. Additionally, bonds are issued to banks as support for letters of credit provided by those banks. As of September 30, 2026, the Company had $8.7 million in outstanding other bonds.
Asset Retirement Obligation
In connection with the acquisition or development of energy storage systems, the Company may have the legal requirement to remove long-lived assets constructed on leased property and to restore the leased property to its condition prior to the construction of the long-lived asset. This legal requirement is referred to as an asset retirement obligation (“ARO”). If the Company determines that an ARO is necessary for a specific energy storage system, the Company records the present value of the estimated future liability when the energy storage system is placed in service as an ARO liability. The Company accretes the ARO liability to its future value over the energy storage system’s useful life in the condensed consolidated statements of operations and comprehensive loss. The initial ARO is recorded as part of the carrying value of the related long-lived asset and depreciated over the energy storage system’s useful life. The CRC energy storage system is the only energy storage system currently subject to an ARO. The initial ARO for the CRC energy storage system was $1.0 million.
The Company measured the ARO for the CRC energy storage system at fair value (Level 3) using an expected present value technique. This approach estimates the cash flows a market participant would require to perform the retirement activities and discounts those cash flows using a credit-adjusted risk-free rate (10.8% at initial recognition).
As of September 30, 2026 and December 31, 2025, the carrying value of the Company’s ARO was $1.1 million and $1.0 million, respectively. For the three and nine months ended September 30, 2026, the Company recognized accretion expense of $28,000 and $0.1 million, respectively. For the three and nine months ended September 30, 2025, the Company recognized accretion expense of $17,000.
McMurtre Project
On March 24, 2026, the Company acquired rights to the McMurtre BESS, a 175 MW / 350 MWh BESS project to be located near Dallas, Texas. The Company paid $0.3 million for the rights to the project and will owe the seller an additional $5.6 million if the project reaches the notice to proceed milestone and $1.4 million if the project reaches commercial operation.
New Mexico Power and Data Center Project
In March 2026, the Company entered into agreements with Public Service Company of New Mexico (“PNM”) for preliminary interconnection, infrastructure planning and engineering work related to the potential development of a battery energy storage, power generation and data center project in Albuquerque, New Mexico. Under these agreements, the Company paid a $7.5 million advance in April 2026 and a $0.5 million nonrefundable engineering deposit in March 2026. Unspent amounts under the $7.5 million agreement are refundable to the extent they have not been fully committed to third parties.
As of September 30, 2026, $6.2 million of the advance and engineering deposit remained recorded in prepaid expenses and other current assets on the condensed consolidated balance sheets.
In April 2026, the Company acquired rights to purchase land in Albuquerque, New Mexico, together with certain development assets. In connection with the acquisition of those rights, the Company paid a nonrefundable assignment fee of $0.8 million. The underlying purchase agreement (the “Land Purchase Agreement”) provided for an aggregate purchase price of approximately $120.1 million for all land tracts. It required the Company to acquire tracts representing $57.4 million of that amount by December 18, 2026 (the “Initial Acquisition Requirement”), and permitted the Company to acquire the remaining tracts before December 18, 2027. If the Company does not satisfy the Initial Acquisition Requirement, the purchase agreement terminates, and the Company’s liability is limited to the forfeiture of the nonrefundable assignment fee. The Company is also required to pay a contingent service fee equal to 7% of the gross purchase price of each acquired tract, payable only upon the closing of each applicable tract.
On October 16, 2026, the Company entered into an amendment to the Land Purchase Agreement. The amendment reduced the Initial Acquisition Requirement to approximately 100 acres and permits the Company to extend the Initial Acquisition Requirement closing deadline from December 18, 2026 to January 4, 2027 by paying a non-refundable extension fee of $25,000 by November 30, 2026, which will count toward payment of the purchase price. If the Company satisfies the Initial Acquisition Requirement, the Company has the right, but not the obligation, to acquire an additional approximately 132 acres by March 19, 2027. The Company may extend that date by making monthly payments of $0.1 million, but the acquisition must close before December 18, 2027. The monthly payments are non-refundable and do not count towards payment of the purchase price. The remaining approximately 254 acres were released from the Land Purchase Agreement.