| Asset Impairment | NOTE 3 – ASSET IMPAIRMENT The Company recorded an impairment loss of $421 and $48 for the three months ended September 30, 2026 and 2025, respectively and $1,513 and $2,472 for the nine months ended September 30, 2026 and 2025, respectively. All 2026 impairments were for specifically identified discrete or non-operable assets, of which $1,138 was impaired at seven RNG sites and $375 at one REG site. The Company did not record any impairments related to its future cash flows assessment. In 2025, $1,983 was impaired for costs related to a development project RNG interconnection for which the local utility is no longer accepting RNG into its distribution system. All associated costs related to the interconnection were impaired. The remaining 2025 impairments of $489 were for specifically identified assets deemed obsolete or non-operable and consisted of $366 within the RNG segment, $120 within the REG segment and $3 within the corporate entity. |