v3.26.3
SAN ONOFRE NUCLEAR GENERATING STATION - NARRATIVE (Details) - San Diego Gas and Electric Company - USD ($)
$ in Millions
Sep. 30, 2026
Jan. 31, 2026
Jointly Owned Nuclear Power Plant    
Jointly Owned Utility Plant Interests [Line Items]    
Jointly owned utility plant, proportionate ownership share (as a percent) 20.00%  
Percent of dismantlement work expense (as a percent) 20.00%  
Decommissioning costs $ 440  
SONGS 2 and 3 Decommissioning    
Jointly Owned Utility Plant Interests [Line Items]    
Nuclear decommissioning trust authorized withdrawal amount   $ 45