Contingencies Contingencies
Legal Proceedings. The Company is party to several pending legal proceedings and claims arising in the normal course of business. The Company records a liability when it is both probable that a liability has been incurred and the amount of the loss can be reasonably estimated. In the event the Company determines that a loss is not probable, but is reasonably possible, and it becomes possible to develop what the Company believes to be a reasonable range of possible loss, then the Company will include disclosure related to such matters. To the extent there is a reasonable possibility that the losses could exceed any amounts accrued, the Company will adjust the accrual in the period the determination is made, disclose an estimate of the additional loss or range of loss, indicate that the estimate is immaterial with respect to its financial statements as a whole or, if the amount of such adjustment cannot be reasonably estimated, disclose that an estimate cannot be made.
On May 13, 2026, the Company received an adverse ruling from the Frankfurt am Main Regional Court in a matter involving Heraeus Metals Germany GmbH & Co. KG (“Heraeus”) related to the theft of 50 kilograms of gold granulate during transport in Germany in 2022. The Company has appealed the ruling. At the time of the incident, the gold was valued at approximately $2.5 million and was valued at approximately $6.7 million as of October 2, 2026, which will fluctuate in future periods as the potential exposure is dependent on future gold prices. The Company expects that approximately $2.5 million of any potential loss will be recoverable under its insurance coverage.
Based on management’s review of the ruling and underlying facts, consultation with legal counsel, and the Company’s appeal, management continues to believe that a loss is not probable at this time. Accordingly, no accrual was recorded at the time of the incident or as of the date of our financial statements. The Company will continue to monitor the appeal process and any changes in facts or circumstances that may affect its assessment.

Environmental Proceedings. The Company has an active environmental compliance program and records reserves for the probable cost of identified environmental remediation projects. The reserves are established based upon analyses conducted by the Company’s engineers and outside consultants and are adjusted from time to time based upon ongoing studies, the difference between actual and estimated costs, and other factors. The reserves may also be affected by rulings and negotiations with regulatory agencies. The undiscounted reserve balance was $2.3 million and $2.5 million at October 2, 2026 and December 31, 2025, respectively, and is included in Other liabilities and accrued items and Other long-term liabilities on the Consolidated Balance Sheet. Environmental projects tend to be long-term, and the final actual remediation costs may differ from the amounts currently recorded.