Regulatory and Rate Matters - Meta Platforms Inc. Data Center - Phase IV, BESS Project (Details) $ in Millions |
Aug. 06, 2025
USD ($)
MW
facility
|
|---|---|
| Public Utilities, General Disclosures [Line Items] | |
| Estimated project costs | $ | $ 78.7 |
| Public Service Company of New Mexico | |
| Public Utilities, General Disclosures [Line Items] | |
| Megawatts of energy storage | MW | 30 |
| Megawatts batteries to be constructed | MW | 6 |
| Public Service Company of New Mexico | Otero, San Miguel and Luna Counties | |
| Public Utilities, General Disclosures [Line Items] | |
| Number of sites | facility | 5 |
| Public Service Company of New Mexico | Valencia County | |
| Public Utilities, General Disclosures [Line Items] | |
| Number of sites | facility | 2 |