Commitments and Contingencies - Coal Supply (Details) - USD ($)
3 Months Ended 9 Months Ended 12 Months Ended
Sep. 30, 2025
Sep. 30, 2026
Sep. 30, 2025
Dec. 31, 2025
San Juan Generating Station        
Public Utilities, Commitments And Contingencies [Line Items]        
Other costs $ 900,000   $ 900,000  
San Juan Generating Station | Underground        
Public Utilities, Commitments And Contingencies [Line Items]        
Increase in regulatory liabilities 200,000   200,000  
San Juan Generating Station | Surface        
Public Utilities, Commitments And Contingencies [Line Items]        
Increase in regulatory liabilities $ 200,000   $ 200,000  
San Juan Generating Station | Maximum        
Public Utilities, Commitments And Contingencies [Line Items]        
Reclamation costs percentage       9.755%
San Juan Generating Station | Minimum        
Public Utilities, Commitments And Contingencies [Line Items]        
Reclamation costs percentage       9.096%
Public Service Company of New Mexico | Four Corners CSA        
Public Utilities, Commitments And Contingencies [Line Items]        
Annual funding post-term reclamation trust       $ 0
Reclamation trust funding, 2026   $ 500,000    
Reclamation trust funding, 2027   500,000    
Reclamation trust funding, 2028   500,000    
Public Service Company of New Mexico | Underground | Loss on long-term purchase commitment        
Public Utilities, Commitments And Contingencies [Line Items]        
Loss contingency accrual   56,900,000   55,200,000
Public Service Company of New Mexico | Surface | Loss on long-term purchase commitment        
Public Utilities, Commitments And Contingencies [Line Items]        
Loss contingency accrual   9,300,000   20,800,000
Public Service Company of New Mexico | San Juan Generating Station | Loss on long-term purchase commitment        
Public Utilities, Commitments And Contingencies [Line Items]        
Annual funding post-term reclamation trust       $ 7,000,000.0
Annual funding post-term reclamation trust, remainder of year   3,400,000    
Annual funding post-term reclamation trust, year one   400,000    
Annual funding post-term reclamation trust, year two   4,700,000    
Public Service Company of New Mexico | San Juan Generating Station and Four Corners | Mine Reclamation Trust        
Public Utilities, Commitments And Contingencies [Line Items]        
Customer reclamation funding cost   100,000,000.0    
San Juan Generating Station | Public Service Company of New Mexico | Underground | Loss on long-term purchase commitment        
Public Utilities, Commitments And Contingencies [Line Items]        
Estimate of possible loss   63,100,000    
San Juan Generating Station | Public Service Company of New Mexico | Surface | Loss on long-term purchase commitment        
Public Utilities, Commitments And Contingencies [Line Items]        
Estimate of possible loss   17,500,000    
San Juan Generating Station | Coal supply        
Public Utilities, Commitments And Contingencies [Line Items]        
Cash used to support bank letter or credit arrangement   19,300,000    
San Juan Generating Station | Coal supply | NM Capital        
Public Utilities, Commitments And Contingencies [Line Items]        
Requirement to post reclamation bonds   118,700,000    
Cash used to support bank letter or credit arrangement   $ 19,300,000