Schedule of Operating Lease

The following table presents balances reported in the consolidated balance sheets related to the Group’s leases:

 

    December 31,
2025
    June 30,
2026
 
    RMB     RMB  
Operating lease right-of-use assets          -       2,346  
Operating lease liabilities     -       2,691  

 

 

Weighted-average remaining term and discount rate related to leases were as follows:

 

    For the six months ended
June 30,
 
    2025     2026  
Cash paid for amounts included in the measurement of lease liabilities:            
Operating cash flows from operating leases     -       -  
Weighted-average remaining term                
Operating lease     -       1.75  
Weighted-average discount rate                
Operating lease     -       3.5 %
Schedule of Future Maturity of Lease Liabilities

As of June 30, 2026, the future maturity of lease liabilities is as follows:

 

    June 30,  
    2026  
    RMB  
Overdue but unpaid     345  
Remainder of 2026     690  
2027     1,380  
2028     345  
Total lease payments     2,760  
Less: interest     (69 )
Present value of lease liabilities     2,691  
Less: Operating lease liabilities, current     1,668  
Operating lease liabilities, non-current     1,023