PAYMENTS MADE UNDER PROTEST |
12 Months Ended | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Jun. 30, 2026 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Payments Made Under Protest [Abstract] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PAYMENTS MADE UNDER PROTEST | PAYMENTS MADE UNDER PROTEST
24PAYMENTS MADE UNDER PROTEST continued
Ekurhuleni Metropolitan Municipality ("Municipality") Electricity Tariff Dispute There are primarily 3 (three) legal proceedings for which relief has been sought in the appropriate legal fora and all of which fall within the jurisdiction of the High Court of South Africa, Gauteng Local Division, Johannesburg. These comprise of an application brought by Ergo and action proceedings brought under two summonses by the Municipality. In order to operate the Ergo Plant and conduct its business operations, Ergo requires a reliable and steady feed of electricity which it has drawn from the newly commissioned Brakpan Tailings 88kV Substation since June 2024. Prior to this the Ergo Plant used to draw electricity from the Ergo Central Substation. Over the past several years the Municipality has charged Ergo for such electricity, at the Megaflex tariff at which ESKOM charges its large power users plus an additional surcharge, as it still does; and Ergo paid consequently. Pursuant to its own investigations, and after having sought legal advice on the matter, Ergo determined that only ESKOM may legitimately charge it for the electricity so drawn and consumed at the Ergo Plant, specifically from the Ergo Central Substation. Despite this, ESKOM refused to either accept payment from Ergo in respect of such electricity consumption or to conclude a consumer agreement with it. In December 2014, Ergo instituted legal proceedings by way of an application (“Main Application”) against the Municipality and ESKOM as well as the National Energy Regulator of South Africa (“NERSA”), the Minister of Energy, the Minister of Co-operative Governance & Traditional Affairs and the South African Local Government Association ("SALGA"), the latter 4 (four) respondents against whom Ergo does not seek any relief. Ergo seeks the undermentioned relief from the High Court: •declaring that the Municipality does not supply electricity to it at the Ergo Plant; •declaring that the Municipality is in breach of its temporary Distribution License (issued by NERSA) by purporting to supply electricity to Ergo at the Ergo Plant; •declaring that neither the Municipality nor ESKOM may lawfully insist that only the Municipality may supply electricity to Ergo at the Ergo Plant; •declaring that ESKOM presently supplies electricity to Ergo at the Ergo Plant; and •directing ESKOM to conclude a consumer agreement with Ergo for the supply of electricity at the Ergo Plant at its Megaflex tariff. The Municipality then issued two summonses (“Summonses”) for the recovery of arrears it alleges it is owed amounting to R74.0 million and R31.6 million, respectively. In the interest of the proper administration of justice, the Main Application was postponed by agreement between the parties and efforts were made to establish a collaborative process to facilitate the effective and efficient court scheduling and coordination of both the Main Application and the Summonses. In order to secure uninterrupted supply of electricity, Ergo has made payment and continues to pay for consumption at the amended and lower “J-Tariff”, albeit under protest and without prejudice and/or admission of liability. Whilst still deemed to be disproportionate, the J-Tariff is significantly lower than the previously imposed “D-Tariff”. The Group recognised an asset for these payments that are made “under protest”. The Group has been advised that an application brought by the SALGA to challenge ESKOM’s ability to supply customers with electricity must be heard, adjudicated and finalised prior to that of the Main Application. The SALGA matter appears to have stalled, due to the interlocutory, joinder applications in the SALGA application. As the SALGA application is pivotal, it is anticipated that any decision handed down will be appealed, finally ending up in the Constitutional Court. 24PAYMENTS MADE UNDER PROTEST continued In an effort to progress these longstanding matters, in August 2024, the Group’s external legal team dispatched correspondence to the Deputy Judge President of the Gauteng Division of the High Court, to request the consolidation of the Main Application and Summonses (Action Proceedings of 2017 and 2019). After much deliberation between the various legal representatives, it was agreed the matters would be consolidated and dealt with, by Judge Adams (appointed Case Manager), through the Case Management process. The Group supported by the external legal team is confident that there is a high probability that Ergo will be successful in the consolidated proceedings and in defending its position. Therefore, there is no present obligation as a result of a past event to pay the amounts claimed by the Municipality (refer note 26.3). The balance at the end of the year was based on the following assumptions: •discount rate: 16.01% (2025: 15.30%) representing the Municipality maximum cost of borrowing on bank loans as disclosed in their 30 June 2026 annual report and an additional risk premium on uncertainties in timing of the SALGA case; and •discount period: 30 June 2034 (2025: 30 June 2029) representing management’s best estimate of the date of conclusion of the Consolidated Application and is supported by external legal counsel.
|