v3.26.3
MINERAL PROPERTY INTERESTS
12 Months Ended
Jun. 30, 2026
MINERAL PROPERTY INTERESTS  
MINERAL PROPERTY INTERESTS

6.MINERAL PROPERTY INTERESTS

(a)

Silver Sand Project

On July 20, 2017, the Company acquired the Silver Sand Project. The Project is located in the Colavi District of the Potosí Department, in Southwestern Bolivia, 33 kilometres (“km”) northeast of Potosí City, the department capital. The project covers an area of approximately 5.42 km2 at an elevation of 4,072 metres (“m”) above sea level.

For the year ended June 30, 2026, total expenditures of $2,705,638 (year ended June 30, 2025 - $1,552,036) were capitalized under the project.

(b)

Carangas Project

In April 2021, the Company signed an agreement with a private Bolivian company to acquire a 98% interest in the Carangas Project. The project is located approximately 180 km southwest of the city of Oruro and within 50 km from Bolivia’s border with Chile. The private Bolivian company is 100% owned by Bolivian nationals and holds title to the three exploration licenses that cover an area of 40.75 km2.

Under the agreement, the Company is required to cover 100% of the future expenditures on exploration, mining, development, and production activities for the project.

For the year ended June 30, 2026, total expenditures of $1,705,078 (year ended June 30, 2025 - $1,473,791) were capitalized under the project.

(c)

Silverstrike Project

In December 2019, the Company acquired a 98% interest in the Silverstrike Project from a private Bolivian corporation. The project covers an area of approximately 13 km2 and is located approximately 140 km southwest of the city of La Paz, Bolivia.

For the year ended June 30, 2026, total expenditures of $76,018 (year ended June 30, 2025 - $62,032) were capitalized under the project.

The continuity schedule of mineral property acquisition costs and deferred exploration and development costs is summarized as follows:

​

​

​

​

​

​

​

​

​

​

​

​

​

​

Cost

  ​ ​ ​

Silver Sand

  ​ ​ ​

Carangas

  ​ ​ ​

Silverstrike

  ​ ​ ​

Total

Balance, June 30, 2024

​

$

88,977,334

​

$

19,854,042

​

$

4,934,555

​

$

113,765,931

Capitalized exploration expenditures

​

 

  ​

​

 

  ​

​

 

  ​

​

 

  ​

Reporting and assessment

​

 

94,894

​

 

190,352

​

 

—

​

 

285,246

Drilling and assaying

​

 

342

​

 

6,763

​

 

5,125

​

 

12,230

Project management and support

​

 

1,155,235

​

 

889,034

​

 

37,828

​

 

2,082,097

Camp service

​

 

179,873

​

 

295,804

​

 

17,033

​

 

492,710

Permit and license

​

 

12,606

​

 

47,818

​

 

—

​

 

60,424

Value added tax not claimed

​

 

109,086

​

 

44,020

​

 

2,046

​

 

155,152

Foreign currency impact

​

 

51,499

​

 

26,018

​

 

3,058

​

 

80,575

Balance, June 30, 2025

​

$

90,580,869

​

$

21,353,851

​

$

4,999,645

​

$

116,934,365

Capitalized exploration expenditures

​

 

  ​

​

 

  ​

​

 

  ​

​

 

  ​

Reporting and assessment

​

 

765

​

 

519,339

​

 

—

​

 

520,104

Drilling and assaying

​

 

11,014

​

 

8,919

​

 

589

​

 

20,522

Project management and support

​

 

1,610,799

​

 

958,627

​

 

55,006

​

 

2,624,432

Camp service

​

 

899,749

​

 

154,812

​

 

19,458

​

 

1,074,019

Permit and license

​

 

6,359

​

 

42,203

​

 

—

​

 

48,562

Value added tax not claimed

​

 

176,952

​

 

21,178

​

 

965

​

 

199,095

Foreign currency impact

​

 

(527,807)

​

 

(181,714)

​

 

(36,361)

​

 

(745,882)

Balance, June 30, 2026

​

$

92,758,700

​

$

22,877,215

​

$

5,039,302

​

$

120,675,217

​