Assets Under Development
6 Months Ended
Jun. 30, 2026
Extractive Industries [Abstract]  
Assets Under Development ASSETS UNDER DEVELOPMENT
June 30, 2026December 31, 2025
(in thousands of $)FLNG EsperanzaFLNG GimiFLNG EsperanzaTotal
Opening balance
1,228,129 1,762,632 498,565 2,261,197 
Transferred from vessels and equipment, net and other current assets— — 76,270 76,270 
Additions162,294 65,381 596,711 662,092 
Interest costs capitalized40,262 38,816 56,583 95,399 
Reimbursement of capital spares invoiced to bp at COD
— (43,152)— (43,152)
Derecognition on commencement of sales-type lease (note 5)
— (1,823,677)— (1,823,677)
Closing balance
1,430,685 — 1,228,129 1,228,129 

12.1 FLNG Gimi

FLNG Gimi achieved COD on June 12, 2025, commencing the 20-year LOA with bp. Upon COD, the asset under development was derecognized and a net investment in a sales-type lease was recognized (see note 7 to the consolidated financial statements included in our 2025 Form 20-F).

12.2 FLNG Esperanza

In September 2024, we entered into an EPC agreement with CIMC Raffles for a FLNG Esperanza with an annual liquefaction capacity of 3.5 MTPA. In February 2025, Fuji LNG, the donor vessel for the FLNG Esperanza, arrived at CIMC Raffles' yard for conversion. Concurrently, the net book value of the vessel of $76.3 million previously included within “Vessels and equipment, net” was reclassified to “Asset under development”.

In September 2024, we issued a $100.0 million letter of credit (“LC”) in favor of B&V with CIMC Raffles. Under the provisions of the LC, the profile reduces over time to reflect payments made by CIMC Raffles under the EPC agreement. There is no associated cash collateral, however a 1.5% upfront fee was paid and a 1.75% annual margin is payable on the outstanding balance which expires in January 2028.

The total estimated budget for the FLNG Esperanza conversion is estimated at $2.2 billion, inclusive of the donor vessel (Fuji LNG), yard supervision, spares, crew, training, contingencies, initial bunker supply and voyage related costs to deliver the FLNG to its operational site, excluding financing costs. The FLNG Esperanza is expected to achieve COD in H2 2028.
As of June 30, 2026, the estimated timing of the outstanding payments is as follows. Of the total amount, $53.6 million and $21.7 million are presented within “Accrued expenses” and “Trade accounts payable”, respectively, in the consolidated balance sheets:

(in thousands of $)
Period ending June 30,
2026 (1)
243,829 
2027445,346 
2028239,024 
202961,246 
Total989,445 
(1) For the six months ending December 31, 2026.