v3.26.1
LEASES (Tables)
12 Months Ended
Jun. 30, 2026
Leases [Abstract]  
Lease, cost
A summary of total lease costs and other information relating to the Company’s finance and operating leases is as follows:
June 30,
($ in millions)202620252024
Total lease cost
Finance lease cost:
Amortization of right-of-use assets
$$$11 
Interest on lease liabilities
— — — 
Operating lease cost
520 496 458 
Short-term lease cost
40 32 45 
Variable lease cost
234 252 227 
Total
$800 $789 $741 
Other information
Cash paid for amounts included in the measurement of lease liabilities:
Financing cash flows from finance leases
$$$10 
Operating cash flows from operating leases
$505 $515 $489 
Right-of-use assets obtained in exchange for new finance lease liabilities$$— $
Right-of-use assets obtained in exchange for new operating lease liabilities$293 $537 $466 
Weighted-average remaining lease term – finance leases
16 years16 years16 years
Weighted-average remaining lease term – operating leases
8 years8 years9 years
Weighted-average discount rate – finance leases
0.2 %0.2 %0.3 %
Weighted-average discount rate – operating leases
3.0 %2.8 %2.8 %
Operating lease liability, maturity schedule
The total future minimum lease payments, over the remaining lease term, relating to the Company’s operating and finance leases for each of the next five fiscal years and thereafter is as follows:
(In millions)Operating LeasesFinance Leases
Fiscal 2027$447 $
Fiscal 2028350 
Fiscal 2029264 
Fiscal 2030209 
Fiscal 2031176 
Thereafter735 17 
Total future minimum lease payments2,181 28 
Less imputed interest(241)— 
Total$1,940 $28 
Finance lease liability, maturity schedule
The total future minimum lease payments, over the remaining lease term, relating to the Company’s operating and finance leases for each of the next five fiscal years and thereafter is as follows:
(In millions)Operating LeasesFinance Leases
Fiscal 2027$447 $
Fiscal 2028350 
Fiscal 2029264 
Fiscal 2030209 
Fiscal 2031176 
Thereafter735 17 
Total future minimum lease payments2,181 28 
Less imputed interest(241)— 
Total$1,940 $28 
Schedule of operating lease and finance lease liabilities included in the consolidated balance sheet
Operating and finance lease liabilities included in the consolidated balance sheet are as follows:
June 30,
20262025
(In millions)Operating LeasesFinance LeasesOperating LeasesFinance Leases
Total current liabilities
$399 $$406 $
Total noncurrent liabilities
1,541 25 1,744 28 
Total
$1,940 $28 $2,150 $31