v3.26.1
PROPERTY, PLANT AND EQUIPMENT (Tables)
6 Months Ended 12 Months Ended
Jun. 30, 2026
Dec. 31, 2025
Property, Plant, and Equipment [Abstract]    
SCHEDULE OF PROPERTY, PLANT AND EQUIPMENT

Property, plant and equipment consist of the following:

 

   June 30,   December 31, 
   2026   2025 
Construction in progress  $379,991,332   $362,667,293 
Land   1,704,675    1,704,675 
Machinery and equipment   9,555,000    9,555,000 
Operations plant   16,397,000    16,397,000 
Total property, plant and equipment  $407,648,007   $390,323,968 

Property, plant and equipment consist of the following:

 

   December 31,   December 31, 
   2025   2024 
Construction in progress  $362,667,293   $324,224,632 
Land   1,704,675    1,260,000 
Machinery and equipment   9,555,000    9,555,000 
Operations plant   16,397,000    16,662,675 
Total property, plant and equipment  $390,323,968   $351,702,307