v3.26.1
LEASE
6 Months Ended
Jun. 30, 2026
Lease  
LEASE

NOTE 10 – LEASE

 

The Company leased warehouse facilities under non-cancelable operating leases with a lease term of two years. Pursuant to the terms of the lease agreements, the Company may apply for renewal three months prior to the expiry of the lease term, subject to the Landlord’s consent. The Landlord has agreed to refund the security deposit upon termination of the leases, provided that the original deposit receipt is returned.

 

Right of use assets and lease liability – right of use are as follows:

 

   June 30, 2026   December 31, 2025 
       (Audited) 
Right-of-use assets  $15,479   $20,425 

 

The lease liability is as follows:

 

   June 30, 2026   December 31, 2025 
       (Audited) 
Current portion  $11,517   $10,920 
Non-current portion   3,962    9,504 
           
Total  $15,479   $20,424 
Total lease liability  $15,479   $20,424 

 

The future minimum lease payment schedule as follows:

For the year ended June 30,  Amount 
2027  $11,517 
2028   3,962 
Total operating lease liabilities  $15,479