Mineral Properties, Plant and Equipment, Net - Schedule of Mineral Properties, Plant and Equipment, Net (Parenthetical) (Details) - USD ($)
$ in Thousands
6 Months Ended 9 Months Ended 12 Months Ended
Jun. 30, 2026
Dec. 31, 2025
Dec. 31, 2025
Property, Plant and Equipment [Line Items]      
Discount amortization $ 2,170 $ 3,403  
Deferred interest cost 5,522 12,978  
Thacker Pass [Member]      
Property, Plant and Equipment [Line Items]      
Prepaid construction costs 88,800 75,000 $ 75,000
Interest on other loans 3,400   3,200
Deferred interest on DOE loan 18,300   2,300
Discount amortization 15,900   9,100
Deferred interest cost 18,500   13,000
Deposits on long-lead equipment $ 243,800 $ 268,700 $ 268,700