Commitments and Contingencies Commitments and Contingencies
The Company maintains certain non-cancelable operating leases that contain various renewal options. (See Note 5 for additional information).
The Company has the following capital commitments related to its investments in real estate ventures:
For the Oklahoma JV, the Company has committed to contribute up to $6.0 million of additional capital to fund pre-development expenditures and land assemblage efforts. As of June 30, 2026, $5.8 million of this contractual commitment remained outstanding. (See Note 3 for additional information).
For Woodland Pointe, the Company is committed to fund up to $16.2 million in capital contributions for future construction of the project to maintain its current ownership interest (85%). As of June 30, 2026, including the Company's initial investment, $10.7 million of this capital commitment remained outstanding. Any additional capital contributions above and beyond the initial investment may be funded at the Company's election, with any failure to fund resulting in a proportional dilution of the Company's original ownership interest. (See Notes 3 and 13 for additional information).
The Company is subject to litigation from time to time in the ordinary course of business; however, the Company does not expect the results, if any, to have a material adverse impact on its results of operations, financial position, or liquidity. The Company records a contingent liability when it is both probable that a liability has been incurred and the amount can be reasonably estimated; however, the Company is not aware of any reasonably possible losses that would have a material impact on its results of operations, financial position, or liquidity. The Company expenses legal defense costs as they are incurred.