| Schedule of Property, Plant, and Equipment, Net |
Property, plant, and equipment, net was comprised of the following: | | | June 30, 2026 | | | December 31, 2025 | | | Cloud service equipment | | $ | 120,999 | | | $ | 146,589 | | | Colocation service equipment | | | 33,511 | | | | 31,875 | | | Purchased and internally developed software | | | 295 | | | | 4,633 | | | Land | | | 11,520 | | | | 6,511 | | | Building | | | 41,360 | | | | - | | | Leasehold improvements | | | 4,044 | | | | 30,088 | | | Other property and equipment | | | 72 | | | | 36 | | | | | | | | | | | | | Less: Accumulated depreciation | | | (45,304 | ) | | | (40,136 | ) | | | | | 166,497 | | | | 179,596 | | | Construction in progress | | | 484,588 | | | | 157,043 | | | Property, plant, and equipment, net | | $ | 651,085 | | | $ | 336,639 | |
|