v3.26.1
Commitments and Contingencies (Tables)
6 Months Ended
Jun. 30, 2026
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Lease, Cost
Supplemental lease expense for the three and six months ended June 30, 2026 and 2025 was as follows (in thousands):
Three Months Ended
June 30,
Six Months Ended
June 30,
2026202520262025
Operating lease cost$405 $472 $823 $956 
Finance lease cost
Amortization of finance leases12 14 26 
Interest on finance lease liabilities— 
Variable lease cost327 385 710 737 
Short-term lease cost11 23 29 
Total lease cost$746 $881 $1,571 $1,751 
Schedule of Asset Acquisition, Contingent Consideration
The following table summarizes the components of the contingent value rights liability in the condensed consolidated balance sheet as of June 30, 2026 and December 31, 2025 (in thousands):
June 30, 2026December 31, 2025
Current Non-Current Current Non-Current
Lease CVR$— $407 $312 $428 
Intellectual Property CVR— — 326 — 
Total CVR liability$— $407 $638 $428