NOTE 11 - COMMITMENTS |
6 Months Ended |
|---|---|
Jun. 30, 2026 | |
| COMMITMENTS | |
| COMMITMENTS | NOTE 11 - COMMITMENTS The Company entered into a construction contract in 2025 for the construction of a new corporate headquarters including a new branch facility for QCBT in Bettendorf, Iowa. The Company will pay the contractor a contract price of approximately $66.5 million, subject to certain agreed upon additions and deductions. As of June 30, 2026, the Company had paid $21.2 million of the contract price, resulting in a remaining future commitment of approximately $45.3 million. Construction on this facility is anticipated to be completed in 2027. |