Commitments |
6 Months Ended |
|---|---|
Jun. 30, 2026 | |
| Commitments [Abstract] | |
| Commitments | 8. Commitments The Company was granted approval by the PPUC to modify its tariff to include the cost of the annual replacement of up to 400 lead customer-owned service lines over nine years from the date of the agreement. The tariff modification allowed the Company to replace customer-owned service lines at its own initial cost. The Company recorded the costs as a regulatory asset to be recovered in future base rates to customers, over a four-year period. The cost for the customer-owned lead service line replacements was approximately $2,093 and $2,087 through June 30, 2026 and December 31, 2025, respectively, and is included as a regulatory asset. The tariff modification expired on March 8, 2026. The Company has filed a Lead Service Line Replacement Plan with the PPUC and is awaiting a decision. If approved, the plan would establish the requirements for, and the associated cost recovery mechanisms related to, the future replacement of customer‑owned lead service lines.
|