v3.26.1
COMMITMENTS AND CONTINGENCIES (Tables)
6 Months Ended
Jun. 30, 2026
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Components of Lease Expense
The elements of lease expense were as follows:
For the Six Months Ended June 30,
(in thousands)20262025
Lease Cost
Operating lease cost$965 $964 
Short-term lease cost273 391 
Variable lease cost210 245 
Sublease income(263)— 
Total Lease Cost$1,185 $1,600 
Other Information
Operating cash flows used for operating leases997 969 
Operating Leases
Weighted-average remaining lease term (in years)3.14.1
Operating Leases
Weighted-average discount rate9.2 %9.2 %
Schedule of Future Lease Payments under Non-Cancelable Leases
Future minimum lease payments under non-cancelable operating leases with terms of greater than one year as of June 30, 2026, were as follows:
(in thousands)Amount
2026 (remainder of year)$1,022 
20272,078 
20282,140 
20291,269 
Total lease payments$6,509 
Less: imputed interest829 
Total operating lease liabilities$5,680