v3.26.1
LEASES - Additional Information (Details)
1 Months Ended 3 Months Ended 6 Months Ended
Oct. 31, 2025
renewalOption
MW
Sep. 30, 2025
renewalOption
Oct. 31, 2024
a
renewalOption
Jun. 30, 2026
USD ($)
Jun. 30, 2025
USD ($)
Jun. 30, 2026
USD ($)
Jun. 30, 2025
USD ($)
Mar. 31, 2026
Dec. 31, 2025
USD ($)
Nov. 22, 2022
Lessee, Lease, Description [Line Items]                    
Purchase obligation with call option to purchase | $       $ 25,512,000   $ 25,512,000     $ 0  
Finance lease initial term                   5 years
Variable lease costs | $       $ 0 $ 0 $ 0 $ 0      
Barber Lake Facility Lease                    
Lessee, Lease, Description [Line Items]                    
Lease not yet commenced, term of contract   10 years                
Lease not yet commenced, number of renewal options   2                
Lease not yet commenced, renewal term   5 years                
Lease With Investment Grade Hyperscaler Tenant, Fifteen Year Term                    
Lessee, Lease, Description [Line Items]                    
Lease not yet commenced, term of contract 15 years                  
Lease not yet commenced, number of renewal options 3                  
Lease not yet commenced, renewal term 5 years                  
Power generation capacity of turnkey data center (in MW) | MW 300                  
Data Center Lease With Investment Grade Hyperscaler Tenant, Fifteen Year Term                    
Lessee, Lease, Description [Line Items]                    
Lease not yet commenced, term of contract               15 years    
Reveille Lease Agreement | Land                    
Lessee, Lease, Description [Line Items]                    
Area of lease plot land (in acres) | a     52              
Operating lease initial term     10 years              
Number of renewal options for lease     2              
Operating lease, renewal term     10 years