RELATED PARTY                
Amount of potential DoE funding       $ 21,900        
Percentage of total estimated cost for the project covered by DoE funding       0.50%        
Allowable costs for planned demonstration funded on cost share basis       $ 43,800        
Percentage of total cost of the demonstration plant funded by DoE   0.50%   50.00%        
Percentage of total cost of the demonstration plant funded by non federal entity       50.00%        
Subcontracted services   0.50%            
Demonstration plant project budget               $ 53,600
Expenses of Demonstration           $ 62,183    
General Atomics                
RELATED PARTY                
Percentage of total cost of the demonstration plant funded by non federal entity     50.00%          
Commitment amount   $ 5,318            
Demonstration plant project budget   $ 53,600         $ 53,600  
Demonstration plant project budget increase percentage   22.00%            
Demonstration plant project original budget   $ 43,800            
Additional cost-share funding   $ 2,400            
Projected operating cost           82,000    
Maximum additional cash advances for project funding agreement for project completion $ 2,500         4,746    
Payments for advance payments under project funding 24,200         20,389    
Funds returned by General Atomics during the year $ 3,811              
Payments for demonstration plant project costs         $ 4,746 $ 16,593