Regulatory Matters - ACC General Retail Rate Cases (Details)
$ in Millions
May 11, 2026
USD ($)
May 01, 2026
USD ($)
Apr. 03, 2026
USD ($)
Mar. 18, 2026
USD ($)
Mar. 02, 2026
USD ($)
Jun. 13, 2025
USD ($)
$ / KWH_Kilowatt_hour
Feb. 22, 2024
USD ($)
Apr. 02, 2026
Public Utilities, General Disclosures [Line Items]                
Requested rate increase (decrease), amount   $ 506.5   $ 525.2        
Increment of fair value rate, percentage         0.00%      
Requested period of post-test year plant       12 months        
Requested increase (decrease) in deadband   0.0050            
Approved rate increase (decrease), amount             $ 491.7  
Minimum                
Public Utilities, General Disclosures [Line Items]                
Requested rate increase (decrease), amount         $ 200.2      
Requested return on equity, percentage       9.55% 9.00%      
Requested period of post-test year plant         0 months      
Maximum                
Public Utilities, General Disclosures [Line Items]                
Requested rate increase (decrease), amount         $ 278.1      
Requested return on equity, percentage       9.80% 9.20%      
Requested period of post-test year plant         12 months      
APS                
Public Utilities, General Disclosures [Line Items]                
Requested rate increase (decrease), amount $ 691.6   $ 694.2          
Requested return on equity, percentage     10.70%          
Increment of fair value rate, percentage     0.90%         1.00%
Requested period of post-test year plant     12 months          
Requested net revenue requirement increase (decrease), amount $ 608.7   $ 611.3          
Requested increase (decrease) in deadband     0.0040          
Requested projected plant duration     6 months          
Requested review and challenge period     120 days          
ACC                
Public Utilities, General Disclosures [Line Items]                
Increment of fair value rate, percentage       0.20%     0.25%  
Approved return on equity, percentage             9.55%  
ACC | APS                
Public Utilities, General Disclosures [Line Items]                
Requested rate increase (decrease), amount           $ 579.5    
Total revenue deficiency           $ 662.4    
ACC | APS | Rate Case Filing with Arizona Corporation Commission                
Public Utilities, General Disclosures [Line Items]                
Requested rate increase (decrease), percentage           13.99%    
Public utilities, test period           12 months    
Rate matter, cost base rate           $ 12,500.0    
Effective fair value percentage             4.39%  
ACC | ACC | Rate Case Filing with Arizona Corporation Commission                
Public Utilities, General Disclosures [Line Items]                
Base fuel and purchased power costs rate (in dollars per kWh) | $ / KWH_Kilowatt_hour           0.043881