The following tables provide a summary of financial information related to the Company’s segments (in thousands):
Three Months Ended June 30, 2026
Marigold
CC&V
Seabee
Puna
Segment Total
Corporate and other (1)
Total from Continuing Operations
Revenue$127,376 $129,094 $65,311 $122,017 $443,798 $— $443,798 
Cost of sales (2)
$58,843 $44,488 $27,016 $43,325 $173,672 $— $173,672 
Depreciation, depletion, and amortization$8,096 $4,820 $12,218 $5,839 $30,973 $79 $31,052 
General and administrative expense$— $— $— $— $— $27,649 $27,649 
Exploration and evaluation$219 $225 $1,619 $3,964 $6,027 $2,932 $8,959 
Reclamation and remediation costs
$890 $4,643 $336 $1,280 $7,149 $— $7,149 
Other operating expense (income), net
$1,177 $(110)$44 $297 $1,408 $2,233 $3,641 
Operating income (loss)$58,151 $75,028 $24,078 $67,312 $224,569 $(32,893)$191,676 
Interest expense
$— $(3)$— $(29)$(32)$(361)$(393)
Interest income
$121 $187 $61 $424 $793 $4,031 $4,824 
Other income (expense)
$(210)$1,528 $$6,319 $7,642 $(99)$7,543 
Foreign exchange gain (loss)$— $$(302)$(13,294)$(13,595)$(4,723)$(18,318)
Income (loss) before income and mining taxes
$58,062 $76,741 $23,842 $60,732 $219,377 $(34,045)$185,332 
Capital expenditures$40,188 $19,442 $11,058 $9,757 $80,445 $— $80,445 
Total assets as of June 30, 2026
$947,676 $727,212 $393,261 $316,327 $2,384,476 $1,894,814 $4,279,290 
(1)Corporate and other consists of business activities that are not included within the reportable segments and is provided for reconciliation purposes. The exploration, evaluation and development properties and the portfolio of prospective exploration tenures, near or adjacent to the existing operations, are included in the respective reportable segment. The greenfield standalone prospects and development projects are included in Corporate and other.
(2)Excludes depreciation, depletion, and amortization.
Three Months Ended June 30, 2025
Marigold
CC&V
Seabee (1)
PunaSegment Total
Corporate and other (2)
Total from Continuing Operations
Revenue$118,786 $149,965 $34,540 $102,164 $405,455 $— $405,455 
Cost of sales (3)
$56,376 $50,003 $18,473 $38,096 $162,948 $— $162,948 
Depreciation, depletion, and amortization$8,228 $2,784 $6,921 $8,191 $26,124 $80 $26,204 
General and administrative expense
$— $— $— $— $— $26,634 $26,634 
Exploration and evaluation
$1,824 $(195)$2,743 $805 $5,177 $880 $6,057 
Reclamation and remediation costs
$806 $3,887 $336 $1,280 $6,309 $— $6,309 
Care and maintenance (4)
$— $— $1,013 $— $1,013 $— $1,013 
Other operating expense (income), net
$313 $630 $98 $203 $1,244 $6,970 $8,214 
Operating income (loss)$51,239 $92,856 $4,956 $53,589 $202,640 $(34,564)$168,076 
Interest expense$— $— $— $(877)$(877)$(1,708)$(2,585)
Interest income$756 $— $303 $907 $1,966 $1,057 $3,023 
Other income (expense)$(246)$— $(7)$3,954 $3,701 $(730)$2,971 
Foreign exchange gain (loss)$— $— $854 $(6,235)$(5,381)$(4,837)$(10,218)
Income (loss) before income and mining taxes
$51,749 $92,856 $6,106 $51,338 $202,049 $(40,782)$161,267 
Capital expenditures$18,841 $14,427 $8,762 $4,023 $46,053 $759 $46,812 
Total assets as of June 30, 2025
$818,746 $534,551 $355,909 $363,386 $2,072,592 $358,728 $2,431,320 
(1)During the second quarter of 2025, the Company suspended operations at Seabee for approximately two weeks due to power interruptions caused by forest fires to the north of the mine. Seabee resumed operations on June 13, 2025.
(2)Corporate and other consists of business activities that are not included within the reportable segments and is provided for reconciliation purposes. The exploration, evaluation and development properties and the portfolio of prospective exploration tenures, near or adjacent to the existing operations, are included in the respective reportable segment. The greenfield standalone prospects and development projects are included in Corporate and other.
(3)Excludes depreciation, depletion, and amortization.
(4)Care and maintenance expense represents the direct costs of $0.2 million and depreciation of $0.8 million during the temporary suspension of operations at Seabee during the three months ended June 30, 2025.
Six Months Ended June 30, 2026
Marigold
CC&V
Seabee
Puna
Segment Total
Corporate and other (1)
Total from Continuing Operations
Revenue$315,015 $315,546 $93,757 $301,258 $1,025,576 $— $1,025,576 
Cost of sales (2)
$130,477 $99,234 $48,261 $90,819 $368,791 $— $368,791 
Depreciation, depletion, and amortization$18,095 $10,199 $19,154 $13,550 $60,998 $159 $61,157 
General and administrative expense$— $— $— $— $— $66,130 $66,130 
Exploration and evaluation$462 $248 $3,434 $6,084 $10,228 $4,035 $14,263 
Reclamation and remediation costs
$1,779 $8,636 $672 $2,560 $13,647 $— $13,647 
Other operating expense (income), net$4,020 $533 $443 $521 $5,517 $3,940 $9,457 
Operating income (loss)$160,182 $196,696 $21,793 $187,724 $566,395 $(74,264)$492,131 
Interest expense$— $(11)$(12)$(24)$(47)$(1,615)$(1,662)
Interest income$324 $327 $265 $745 $1,661 $6,323 $7,984 
Other income (expense) $(413)$1,915 $(17)$11,252 $12,737 $(406)$12,331 
Foreign exchange gain (loss)$— $$(217)$(7,717)$(7,933)$(4,644)$(12,577)
Income (loss) before income and mining taxes$160,093 $198,928 $21,812 $191,980 $572,813 $(74,606)$498,207 
Capital expenditures$65,861 $26,919 $28,866 $14,502 $136,148 $— $136,148 
Total assets as of June 30, 2026
$947,676 $727,212 $393,261 $316,327 $2,384,476 $1,894,814 $4,279,290 
(1)Corporate and other consists of business activities that are not included within the reportable segments and is provided for reconciliation purposes. The exploration, evaluation and development properties and the portfolio of prospective exploration tenures, near or adjacent to the existing operations, are included in the respective reportable segment. The greenfield standalone prospects and development projects are included in Corporate and other.
(2)Excludes depreciation, depletion, and amortization.
Six Months Ended June 30, 2025
Marigold
CC&V (1)
Seabee (2)
Puna
Segment Total
Corporate and other (3)
Total from Continuing Operations
Revenue$235,966 $184,837 $110,842 $190,428 $722,073 $— $722,073 
Cost of sales (4)
$115,102 $67,968 $41,604 $74,915 $299,589 $— $299,589 
Depreciation, depletion, and amortization$16,941 $3,288 $20,425 $15,972 $56,626 $159 $56,785 
General and administrative expense$— $— $— $— $— $50,529 $50,529 
Exploration and evaluation$2,515 $— $6,883 $1,177 $10,575 $1,442 $12,017 
Reclamation and remediation costs$1,610 $5,171 $672 $2,561 $10,014 $— $10,014 
Care and maintenance (5)
$— $— $1,013 $— $1,013 $— $1,013 
Other operating expense (income), net$656 $634 $98 $439 $1,827 $15,407 $17,234 
Operating income (loss)$99,142 $107,776 $40,147 $95,364 $342,429 $(67,537)$274,892 
Interest expense$— $— $— $(982)$(982)$(3,395)$(4,377)
Interest income$2,356 $— $731 $1,253 $4,340 $1,680 $6,020 
Other income (expense) $(459)$— $(15)$7,778 $7,304 $(1,068)$6,236 
Foreign exchange gain (loss)$— $— $746 $(9,920)$(9,174)$(5,675)$(14,849)
Income (loss) before income and mining taxes$101,039 $107,776 $41,609 $93,493 $343,917 $(75,995)$267,922 
Capital expenditures$34,091 $15,820 $20,564 $5,977 $76,452 $— $76,452 
Total assets as of June 30, 2025
$818,746 $534,551 $355,909 $363,386 $2,072,592 $358,728 $2,431,320 
(1)The reported statements of operations amounts reflect results for CC&V from the date of acquisition on February 28, 2025 through June 30, 2026.
(2)During the second quarter of 2025, the Company suspended operations at Seabee for approximately two weeks due to power interruptions caused by forest fires to the north of the mine. Seabee resumed operations on June 13, 2025.
(3)Corporate and other consists of business activities that are not included within the reportable segments and is provided for reconciliation purposes. The exploration, evaluation and development properties and the portfolio of prospective exploration tenures, near or adjacent to the existing operations, are included in the respective reportable segment. The greenfield standalone prospects and development projects are included in Corporate and other.
(4)Excludes depreciation, depletion, and amortization.
(5)Care and maintenance expense represents the direct costs of $0.2 million and depreciation of $0.8 million during the temporary suspension of operations at Seabee during the six months ended June 30, 2025.