v3.26.1
Commitments and Contingencies (Schedule of Subsidiary Guarantees) (Parenthetical) (Detail)
1 Months Ended 6 Months Ended
Jul. 31, 2024
Jul. 31, 2016
Jun. 30, 2026
Agreement with Lessor to Complete Construction and Lease Jones Act Compliant Offshore Wind Installation Vessel      
Guarantee Obligations [Line Items]      
Lease agreement maturity period     5 years
Lessor | New Corporate Office | Agreement with Lessor to Construct and Lease Corporate Office Property      
Guarantee Obligations [Line Items]      
Lease commenced term   5 years  
Lease commencement period   2019-08  
Lessee, operating Lease, existence of option to extend true    
Lessee operating lease extended maturity period 2029-07    
Lessor | New Corporate Office | Agreement with Lessor to Construct and Lease Corporate Office Property | Minimum      
Guarantee Obligations [Line Items]      
Lease extend term     1 year