v3.26.1
Construction Backlog (Tables)
3 Months Ended
Mar. 31, 2026
Construction Backlog [Abstract]  
Schedule of Backlog of Signed Construction and Engineering Contracts

The following represents the backlog of signed construction and engineering contracts in existence at March 31, 2026 and December 31, 2025, which represents the amount of revenue the Company expects to realize from work to be performed on uncompleted contracts in progress and from contractual agreements in effect at such dates on which work has not yet begun:

 

    Three Months
Ended
March 31,
2026
    Year
Ended
December 31,
2025
 
Balance - beginning of period   $ 271,128     $ 1,182,955  
New contracts and change orders during the period     1,109,456       1,199,839  
Subtotal     1,380,584       2,382,794  
Less: contract revenue earned during the period     (100,740 )     (2,111,666 )
Balance - end of period   $ 1,279,844     $ 271,128