COMMITMENTS AND CONTINGENCIES |
6 Months Ended |
|---|---|
Jun. 30, 2026 | |
| Commitments and Contingencies Disclosure [Abstract] | |
| COMMITMENTS AND CONTINGENCIES | (3) COMMITMENTS AND CONTINGENCIES In October 2025, the Company entered into an agreement for one new drilling rig, with a pad to pad contract term. Comstock took delivery of this rig in January 2026. Remaining commitments for drilling rigs on pad to pad agreements total $15.9 million as of June 30, 2026. From time to time, the Company is involved in certain litigation that arises in the normal course of its operations. The Company records a loss contingency for these matters when it is probable that a liability has been incurred and the amount of the loss can be reasonably estimated. The Company does not believe the resolution of these matters will have a material effect on the Company's financial position, results of operations or cash flows and no material amounts are accrued relative to these matters at June 30, 2026 or 2025. |