Commitments and Contingencies (Tables)
6 Months Ended
Jun. 30, 2026
Commitments and Contingencies [Abstract]  
Schedule of Planned Capital Expenditures
As of June 30, 2026, estimated capital expenditures, on an accrual basis, for the remainder of 2026 through 2030 were as follows:

 Remainder of 20262027202820292030Total
 (millions)
FPL:
Generation:(a)
New(b)
$2,170 $4,330 $4,010 $4,820 $4,225 $19,555 
Existing3301,3601,3001,3001,3505,640 
Transmission and distribution(c)
2,1954,9104,7755,9006,72024,500 
Nuclear fuel1453454503903801,710 
General and other5457557406656203,325 
Total$5,385 $11,700 $11,275 $13,075 $13,295 $54,730 
NEER:(d)
      
Wind(e)
$915 $1,485 $3,220 $190 $115 $5,925 
Solar(f)
5,810 6,690 3,555 95 450 16,600 
Other clean energy(g)
2,655 4,070 1,660 35 10 8,430 
Nuclear, including nuclear fuel470 1,110 875 510 455 3,420 
Regulated electric and gas transmission
545 1,025 760 680 905 3,915 
Other320 370 325 345 370 1,730 
Total$10,715 $14,750 $10,395 $1,855 $2,305 $40,020 
———————————————
(a)Includes AFUDC of approximately $115 million, $265 million, $245 million, $275 million and $235 million for the remainder of 2026 through 2030, respectively.
(b)Includes land, generation structures, transmission interconnection and integration and licensing.
(c)Includes AFUDC of approximately $45 million, $95 million, $105 million, $165 million and $160 million for the remainder of 2026 through 2030, respectively.
(d)Represents capital expenditures for which applicable internal approvals and also, if required, regulatory approvals have been received.
(e)Consists of capital expenditures for new wind projects and repowering of existing wind projects totaling approximately 3,637 MW, and related transmission.
(f)Includes capital expenditures for new solar projects (including solar plus battery storage projects) totaling approximately 16,245 MW and related transmission.
(g)Includes capital expenditures primarily for battery storage projects totaling approximately 6,115 MW and related transmission, as well as renewable fuels projects.
Required capacity and/or minimum payments under contracts
The required capacity and/or minimum payments under contracts, including those discussed above, as of June 30, 2026 were estimated as follows:

Remainder of 20262027202820292030Thereafter
(millions)
FPL(a)
$625 $1,195 $1,165 $1,160 $1,195 $8,145 
NEER(b)(c)
$5,395 $4,255 $720 $250 $170 $490 
———————————————
(a)Includes approximately $215 million, $430 million, $430 million, $425 million, $425 million and $4,540 million for the remainder of 2026 through 2030 and thereafter, respectively, of firm commitments related to natural gas transportation agreements with affiliates. The charges associated with these agreements are recoverable through the fuel clause. For the three and six months ended June 30, 2026, the charges associated with these agreements totaled approximately $108 million and $208 million, respectively. For the three and six months ended June 30, 2025, the charges associated with these agreements totaled approximately $104 million and $204 million, respectively.
(b)Includes approximately $150 million of commitments to invest in technology and other investments through 2032. See Note 7 – Other.
(c)Includes approximately $1,585 million and $1,170 million for the remainder of 2026 and 2027, respectively, of joint obligations of NEECH and NEER.