Leases (Tables)
|
12 Months Ended |
Mar. 31, 2026 |
| Leases [Abstract] |
|
| Balance Sheet Information for Leases |
Balance sheet information for leases is comprised of the following:
| | | | | | | | | | | |
| |
|
|
| |
March 31, 2026
| |
| |
March 31, 2025
| |
|
Leases
|
|
Classification
|
| | | |
| | | |
|
Assets:
|
|
|
| | | |
| | | |
|
Operating
|
|
Operating lease assets |
| $ | 63,103,000 | |
| $ | 66,603,000 | |
|
Finance
|
|
Plant and equipment |
| | 4,784,000 | |
| | 4,296,000 | |
|
Total leased assets
|
|
| $ | 67,887,000 | |
| $ | 70,899,000 | |
| |
|
|
| | | |
| | | |
|
Liabilities:
|
|
|
| | | |
| | | |
|
Current
|
|
|
| | | |
| | | |
|
Operating
|
|
Operating lease liabilities |
| $ | 8,957,000 | |
| $ | 9,982,000 | |
|
Finance
|
|
Other current liabilities |
| | 1,289,000 | |
| | 1,222,000 | |
|
Long-term
|
|
|
| | | |
| | | |
|
Operating
|
|
Long-term operating lease liabilities |
| | 56,969,000 | |
| | 65,308,000 | |
|
Finance
|
|
Other liabilities |
| | 3,202,000 | |
| | 1,954,000 | |
|
Total lease liabilities
|
|
| $ | 70,417,000 | |
| $ | 78,466,000 | |
|
| Lease Cost Recognized in Consolidated Statement of Operations |
Lease cost recognized in the consolidated statements of operations is comprised of the following:
| | | | | | | | | | | | | |
| |
| |
Years Ended March 31,
|
|
| |
| |
2026
| |
| |
2025
| |
| |
2024
| |
|
Lease cost
|
| | | |
| | | |
| | | |
|
Operating lease cost
|
| $ | 14,357,000 | |
| $ | 14,057,000 | |
| $ | 15,047,000 | |
|
Short-term lease cost
|
| | 999,000 | |
| | 1,221,000 | |
| | 1,263,000 | |
|
Variable lease cost
|
| | 592,000 | |
| | 511,000 | |
| | 667,000 | |
|
Finance lease cost:
|
| | | |
| | | |
| | | |
|
Amortization of finance lease assets
|
| | 1,294,000 | |
| | 1,234,000 | |
| | 1,508,000 | |
|
Interest on finance lease liabilities
|
| | 297,000 | |
| | 191,000 | |
| | 219,000 | |
|
Total lease cost
|
| $ | 17,539,000 | |
| $ | 17,214,000 | |
| $ | 18,704,000 | |
|
| Maturity of Lease Commitments |
Maturities of lease commitments were as follows:
| | | | | | | | | | | | | |
|
Maturity of lease liabilities by year ended March 31,
|
| |
Operating Leases
| |
| |
Finance Leases
| |
| |
Total
| |
|
2027
|
| $ | 12,454,000 | |
| $ | 1,547,000 | |
| $ | 14,001,000 | |
|
2028
|
| | 11,806,000 | |
| | 1,292,000 | |
| | 13,098,000 | |
|
2029
|
| | 11,285,000 | |
| | 1,027,000 | |
| | 12,312,000 | |
|
2030
|
| | 11,387,000 | |
| | 950,000 | |
| | 12,337,000 | |
|
2031
|
| | 11,623,000 | |
| | 269,000 | |
| | 11,892,000 | |
|
Thereafter
|
| | 20,529,000 | |
| | - | |
| | 20,529,000 | |
|
Total lease payments
|
| | 79,084,000 | |
| | 5,085,000 | |
| | 84,169,000 | |
|
Less: amount representing interest
|
| | (13,158,000 | ) |
| | (594,000 | ) |
| | (13,752,000 | ) |
|
Present value of lease liabilities
|
| $ | 65,926,000 | |
| $ | 4,491,000 | |
| $ | 70,417,000 | |
|
| Other Information about Leases |
Other information about leases is as follows:
| | | | | | | | | | | | | | March 31, 2026 | | | | March 31, 2025 | | | Lease term and discount rate | | | | | | | | | | Weighted-average remaining lease term (years): | | | | | | | | | | Finance leases | | | 3.8 | | | | 3.2 | | | Operating leases | | | 6.5 | | | | 7.3 | | | Weighted-average discount rate: | | | | | | | | | | Finance leases | | | 6.8 | % | | | 7 | % | | Operating leases | | | 5.7 | % | | | 5.8 | % |
|