v3.26.1
COMMITMENTS AND CONTINGENCIES (Tables) - Chengdu Lease [Member]
12 Months Ended
Dec. 31, 2025
Collaborative Arrangement and Arrangement Other than Collaborative [Line Items]  
SCHEDULE OF OPERATING LEASE COST

Balance sheet information related to the Company’s operating leases:

  

As of

December 31, 2025

  

As of

December 31,

2024

 
Right-of-used assets   299,018   $166,727 
Lease liabilities – current   131,728   $130,483 
Lease liabilities – non-current   170,605    38,125 
Total lease liabilities   302,333   $168,608 

 

 

The weighted-average remaining lease term and the weighted-average discount rate of the above two leases are as follows:

 

    Year Ended December 31, 2025 
      
Weighted average remaining lease term (years)   2.30 
Weighted average discount rate   6.87-10.00%
Sichuan Hongzuo Shuya Energy Limited [Member]  
Collaborative Arrangement and Arrangement Other than Collaborative [Line Items]  
SCHEDULE OF LEASE PAYMENT

The following is a schedule, by year of lease payment for above two leases as of December 31, 2025:

 

For the 12 months ending   Lease Payment 
      
December 31, 2026   154,805 
2027   122,239 
2028   

60,529

 
Total undiscounted cash flows   337,573 
Imputed Interest   35,240 
Present value of lease liabilities  $302,333