v3.26.1
Payments, by Project - 12 months ended Dec. 31, 2025 - USD ($)
Taxes
Fees
Total Payments
Fox Complex      
Total $ 240,000 $ 180,000 $ 420,000
Gold Bar 306      
Total $ 1,340,000 230,000 1,570,000
Gold Bar 307      
Total   500,000 500,000
Gold Bar South 317      
Total   40,000 40,000
Tonkin 101      
Total   320,000 320,000
Cornerstone 207      
Total   10,000 10,000
Slaven Canyon 313      
Total   10,000 10,000
South Midas 315      
Total   30,000 30,000
New Pass 310      
Total   20,000 20,000
Lookout Mountain Project      
Total   120,000 120,000
Windfall Project      
Total   60,000 60,000
Oswego Project      
Total   50,000 50,000
Seven Troughs Project      
Total   50,000 50,000
El Gallo Project      
Total   $ 2,230,000 $ 2,230,000