The Company is preparing the Tonopah property site for the construction of a permitted custom processing toll milling facility including grading the land, installing fencing, and working with contractors for our planned 21,875 square foot building and servicing and drilling various wells for our future operations. 

 

The Company evaluates its mineral rights for impairment whenever events or changes in circumstances indicate that the carrying amount may not be recoverable, in accordance with ASC 360-10. During Q1 2026, management performed a qualitative assessment considering current commodity prices, the status of permitting activities, the condition of the underlying property, and the Company’s intent and ability to develop the property. Based on this assessment, management concluded that no indicators of impairment existed and the carrying value of $3,883,524 was recoverable as of March 31, 2026.