Commitments and Contingencies |
3 Months Ended |
|---|---|
Mar. 31, 2026 | |
| Commitments and Contingencies | |
| Commitments and Contingencies | Note 12 – Commitments and Contingencies
The Company is from time to time subject to legal proceedings and claims that arise in the ordinary course of business.
On January 29, 2026, Carambolico LTD commenced a lawsuit, captioned Carambolico LTD v. Alot, Inc., No. 04CV-26-458 (Ark. Cir. filed Jan. 29, 2026), in the Circuit Court of Benton County, Arkansas, naming Alot, Inc., a wholly owned subsidiary of the Company, as defendant. The complaint asserts breach of contract and related claims under a services agreement and seeks $1.5 million in damages. The Company believes the claims are without merit and intends to vigorously defend the matter.
In April 2026, AEM Days Ltd. commenced a lawsuit, captioned AEM Days Ltd. v. Alot, Inc., No. 60CV-26-3363 (Ark. Cir. filed Apr. 2026), in the Circuit Court of Pulaski County, Arkansas, naming Alot, Inc., a wholly owned subsidiary of the Company, as defendant. The complaint asserts claims related to a services agreement and seeks approximately $766,000 in unpaid invoices. The Company believes the claims are without merit and intends to vigorously defend the matter.
In each of the above matters, the Company is currently unable to predict the outcome or estimate a range of reasonably possible loss, if any. No liability has been accrued as of March 31, 2026. |