v3.26.1
Commitments and Contingencies
3 Months Ended
Mar. 31, 2026
Commitments and Contingencies.  
Commitments and Contingencies

9.           Commitments and Contingencies

See Note 9 – Commitments and Contingencies to the Consolidated Financial Statements contained in our Annual Report on Form 10-K for the year ended December 31, 2025, for additional details regarding the Company’s commitments.

a.Mining Claim Assessments

The Company currently holds mining claims and mill sites for which it has an annual assessment obligation of $0.3 million to maintain the claims in good standing. The Company is committed to these payments indefinitely.

b.Option Payments on Other Properties

The Company is obligated to make option payments on mineral properties in order to maintain an option to purchase these properties. As of March 31, 2026, the option payments due on these properties during 2026 is $0.03 million. The agreements include options to extend.

c.Financial Assurance

In the fourth quarter of 2025, in connection with the conditional Notice to Proceed from the USFS for the Stibnite Gold Project, which required the Company to post joint construction phase financial assurance agreed to by the USFS, Idaho Department of Lands (“IDL”) and U.S. Army Corps of Engineers (“USACE”), the Company entered into multiple related financial agreements to satisfy the financial assurance requirements necessary to commence construction. The Company’s financial assurance obligations may be adjusted by applicable regulators to reflect changes to reclamation costs as construction proceeds. Financial assurance obligations are also subject to adjustment when the Project transitions to operations. There were no changes in financial assurance during the three months ended March 31, 2026.

d.Vendor Deposits - Idaho Power Company

The Company has entered into various agreements with Idaho Power Company (“IPCo”) since the first quarter of 2025 to procure long lead equipment and advance engineering required to increase the electrical capacity to the plant. The Company is responsible for paying relevant costs incurred by IPCo with payment dates and amounts adjusted to reflect specific contracts entered into by IPCo. Changes in the IPCo deposit during the three months ended March 31, 2026 and 2025 are as follows:

  ​ ​ ​

Three months ended March 31, 

In thousands of U.S. Dollars

2026

  ​ ​ ​

2025

Balance at beginning of period

$

15,222

$

Deposits

 

 

18,759

Costs incurred - expense

 

(1,202)

 

(4)

Balance at end of period

$

14,020

$

18,755

Current portion

$

14,020

$

18,755

Non-current portion

 

 

Balance at end of period

$

14,020

$

18,755

e.Vendor Deposits - ATCO

In the third quarter of 2025, the Company entered into a camp supply and installation agreement with ATCO Structures & Logistics (USA) Inc. (“ATCO”) for the design, construction and installation of a 1,010-person turnkey camp accommodation and site package. Changes in the ATCO deposit during the three months ended March 31, 2026 and 2025 are as follows:

Three months ended March 31, 

In thousands of U.S. Dollars

  ​ ​ ​

2026

  ​ ​ ​

2025

Balance at beginning of period

$

12,350

$

Costs incurred – asset

 

(4,368)

 

Balance at end of period

$

7,982

$

Current portion

$

7,982

$

Non-current portion

 

 

Balance at end of period

$

7,982

$

f.Stibnite Foundation

The Stibnite Foundation (“Foundation”) was established in February 2019 to support projects that benefit the communities surrounding the Stibnite Gold Project and created through the execution of the community agreement (the “Community Agreement”), dated November 30, 2018, by and among Perpetua Resources Idaho, Inc. and eight communities and counties throughout the West Central Mountains region of Idaho. There were no changes in Foundation payments or commitments during the three months ended March 31, 2026.

g.Legal Update

The Corporation and its subsidiaries have been parties to an ongoing legal proceeding with the Nez Perce Tribe for claimed violations of the CWA allegedly linked to historical mining activities. In August 2019, the Nez Perce Tribe filed suit against the Company in the U.S. District Court for the District of Idaho. The Company filed an answer generally denying liability and later, the court allowed the Company to amend and file a third-party complaint against the USFS. The Company also filed a separate CWA citizen suit against the USFS alleging that several of the point source discharges, as alleged by the Nez Perce Tribe in its complaint, were occurring on lands owned and controlled by the United States government. Pursuant to the terms of the voluntary ASAOC executed in January 2021 with the EPA and the USDA under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), the Company agreed to dismiss its pending actions against the USFS without prejudice.

On August 8, 2023, the Company and the Nez Perce Tribe filed a final Settlement Agreement (the “Settlement Agreement”) to resolve the Tribe’s CWA claims. The parties jointly asked the court to approve the Settlement Agreement and dismiss the case without prejudice. The Settlement Agreement provides for total payments of $5.0 million by Perpetua over a four-year period. This includes $4.0 million of contributions by Perpetua to the Fund to be used by the Nez Perce Tribe to support water quality improvement projects in the South Fork Salmon River watershed and $1.0 million of reimbursements to the Nez Perce Tribe for legal expenses. Following a 45-day review period by the United States Justice Department and the U.S. EPA, the U.S. District Court for the District of Idaho approved the Stipulation for Dismissal and entered a Judgment on October 2, 2023, which resulted in the CWA lawsuit being dismissed without prejudice. Under the Settlement Agreement, the Company anticipates that a dismissal with prejudice will be entered after completion of Perpetua’s required payments. Once Perpetua has satisfied its payment obligations under the Settlement Agreement, the Company anticipates that the parties will submit a stipulation for dismissal with prejudice to the District Court. The Company recognized an expense of $5.0 million during the second quarter of 2023. During the three months ended March 31, 2026, the Company paid $nil towards this settlement obligation (March 31, 2025 - $nil). As of March 31, 2026, CWA settlement payable current portion is $1.0 million with the remaining $1.0 million classified as long-term.

The voluntary ASAOC entered into by the Company, the U.S. EPA, and the USDA required numerous early cleanup actions (referenced as “Phase 1” in the ASAOC) relating to legacy environmental conditions left by other mining companies. The Company began the Phase 1 activities in 2022. As of March 31, 2026, the Company determined it had completed all Phase 1 response actions required by the ASAOC and filed necessary reports (called Removal Action Completion Report (“RACR”) in the ASAOC) with the U.S. EPA and USDA with respect to such completion. Pursuant to the terms of the ASAOC, the Company’s Phase 1 work will not be considered complete until U.S. EPA and USDA have approved the RACR submitted by the Company. As of March 31, 2026, the RACR remains under review by the federal agencies and no further costs were accrued associated with this Phase 1 liability. The ASAOC includes a process under which the Company and the signatory federal agencies will evaluate whether the Company will proceed with additional response actions after federal agencies confirm that the Phase 1 work has been completed in accordance with the ASAOC requirements. The scope of any such potential additional actions following the completion of Phase 1 and their costs have not yet been determined.

Following the USFS’ publication of the ROD and Final Environmental Impact Statement Errata (the “FEIS”) approving the mine plan for the Project, a lawsuit was filed in the U.S. District Court for the District of Idaho against the USFS, the USDA and other federal agencies on February 18, 2025, in the United States District Court for the District of Idaho by a number of environmental advocacy groups, including Save the South Fork Salmon, the Idaho Conservation League and other non-governmental organizations, alleging violations of NEPA and other federal laws in the regulatory process (“Federal Environmental Case”). Among other remedies, the claimants seek to vacate the ROD, Final Biological Opinions (issued by the U.S. Fish & Wildlife Service and National Marine Fisheries Service), and other Project approvals and to enjoin any further implementation of the Project. PRII filed a motion to intervene in this lawsuit, which was granted by the District Court on April 2, 2025.

On August 29, 2025, the Nez Perce Tribe filed a lawsuit against the USFS, United States Department of Agriculture, and other federal agencies in the U.S. District Court for the District of Idaho the challenging the USFS ROD and other approvals by the USFS and other federal agencies in connection with the Stibnite Gold Project and alleging violations of the NEPA and other federal statutes, regulations, rules and requirements in the regulatory review and approval process in of the Project (“Federal NPT Case”). Among other remedies, the Tribe seeks to vacate the USFS ROD and other Project approvals and to enjoin any further implementation of the Project. PRII filed a motion to intervene in this lawsuit, which was granted by the District Court on September 4, 2025.

The U.S. District Court on October 2, 2025, issued a general order staying all civil cases listed in the order due to the partial shutdown of the federal government over appropriations for the government. The list included the Federal Environmental Case and Federal NPT Case. This stay did not affect the validity of the USFS ROD or any of the other approvals challenged in either of these lawsuits, and all such approvals remain in effect. After the partial shutdown of the federal government ended, the District Court lifted the stay and new scheduling orders were entered in both of these lawsuits challenging the ROD and other approvals of the Project issued by federal agencies. The scheduling order in the Federal Environmental Case required all dispositive motions and briefs to be filed by all parties before the end of January 2026. As of January 20, 2026, all briefs had been submitted. The scheduling order in the Federal NPT Case requires all dispositive motions and briefs to be filed by all parties before the end of June 2026. These two lawsuits remain pending.

On May 8, 2026, the plaintiffs in the Federal Environmental Case filed a motion for a preliminary injunction seeking to delay certain planned construction activities for the Project. The plaintiffs’ motion expressly excluded early works construction activities that were contemplated under previously agreed stipulations between the plaintiffs and the Company and those activities remain ongoing. A decision from the Court on the motion is expected swiftly as plaintiffs in their motion requested a decision by May 30, 2026, and the Court has set a hearing on the motion for May 28, 2026. The Company believes that this motion and the underlying lawsuit are without merit and intends to vigorously oppose the motion. The Company, however, cannot predict the outcome the Court’s decision. If the requested relief is granted, it could delay or restrict further implementation of the Project. As to the merits of the Federal Environmental Case and the Federal NPT Case, the Company believes the USFS ROD and other federal regulatory processes challenged in these lawsuits were conducted thoroughly and completely by the relevant federal regulatory agencies. However, the District Court has not yet ruled on these lawsuits, and the Company cannot predict the outcome or timing of the Court’s ultimate decision on the merits, or in any interim proceedings, in the Federal Environmental Case or the Federal NPT Case. There can be no assurance that the Project approvals challenged in those two lawsuits will be upheld upon judicial review or that the Company will be successful in defending against the challenges raised in the two lawsuits, including the pending motion for a preliminary injunction in the Federal Environmental Case.

The IBEQ published an order on May 27, 2025, upholding the air permit to construct (“PTC”) issued by the IDEQ in June 2022 and denying certain petitioners’ appeal from various administrative proceedings with respect to the PTC. The IBEQ on June 27, 2025, denied the petitioners’ motion for reconsideration. Thereafter, the petitioners filed a petition for judicial review in the Idaho state district court for the County of Ada against the IBEQ and IDEQ seeking to set aside the PTC as violative of applicable law and challenging the decisions of the IBEQ upholding the PTC. IDEQ and the IBEQ thereafter moved to dismiss the complaint on procedural grounds, and the court denied that motion and allowed the petitioners to amend their petition. The petitioners’ amended petition, which names the Company as well as IDEQ and the IBEQ as defendants was served on the Company on or about September 23, 2025. The court entered an order dismissing the IBEQ as a party and requiring all briefs of the parties to be filed by an outside date of January 16, 2026. All briefing was filed as of that date. The court has not ruled on the parties’ dispositive motions, and the cases remain pending. The Company believes that the IDEQ and the IBEQ properly followed Idaho law in issuing the PTC. However, there can be no assurance that the PTC will be upheld upon judicial review.

On March 20, 2025, a putative federal class action lawsuit was filed in the U.S. District Court for the District of Idaho against the Company and certain of its officers and directors, on behalf of a proposed class of purchasers of the Company’s common shares during the period from April 17, 2024 to February 13, 2025, inclusive. The claim, captioned Barnes et al. v. Perpetua Resources Corp. et al., Case No. 1:25-cv-00160, alleges that the defendants violated Sections 10(b) and 20(a) of the Exchange Act and Rule 10b-5 promulgated thereunder by making false and/or misleading statements during the period from April 17, 2024 to February 13, 2025 regarding the Company’s expected capital expenditures for the Stibnite Gold Project. On June 6, 2025, two new plaintiffs filed a joint stipulation seeking to be appointed co-lead plaintiffs, which was granted by the District Court on June 16, 2025. The plaintiffs filed an amended complaint on August 15, 2025. The amended complaint seeks unspecified compensatory damages. The District Court has issued a scheduling order in this case requiring various procedural and substantive motions to be filed by the parties prior to the end of 2025. The Company filed a motion to dismiss the plaintiffs’ amended complaint on September 30, 2025. As of March 31, 2026, all briefs of all parties had been submitted in connection with this motion. The District Court has not ruled on the motion to dismiss, and this lawsuit remains pending. The Company believes that the claim is without merit and intends to vigorously defend itself. However, in view of the uncertainties inherent in litigation, the Company does not express a judgment as to the outcome of this litigation.