Commitments and Contingencies (Tables)
12 Months Ended
Dec. 31, 2025
Commitments and Contingencies [Abstract]  
Schedule of Lease Cost The Company also leases offices in the United Kingdom, France, and Mexico under short-term arrangements of twelve months or less.
   Year ended December 31, 
   2025   2024 
Lease cost:        
Operating lease costs        
Other than related parties  $117,637   $269,915 
Related parties   532,800    524,599 
Total   650,437    794,514 
           
Short-term lease cost          
Other than related parties   43,712    39,145 
Related parties   
-
    
-
 
Total   43,712    39,145 
           
Variable lease cost          
Other than related parties   
--
    9,893 
Related parties   
-
    
-
 
Total   
--
    9,893 
           
Total lease cost  $694,149   $843,552 

 

    Year Ended December 31,  
    2025     2024  
Cash paid for amounts included in the measurement of lease liabilities                
Operating lease costs                
Other than related parties   $ 121,851     $ 269,915  
Related parties    
-
     
-
 
Total   $ 121,851     $ 269,915  
                 
Weight-average remaining lease term-operating leases                
Other than related parties     - years       0.4 years  
Related Parties     - years       - years  
Aggregate     - years       0.4 years  
                 
Weight-average discount rate-operating leases                
Other than related parties     1.79 %     1.79 %
Related Parties    
N/A
%    
N/A
%
Aggregate     1.79 %     1.79 %