v3.26.1
Commitments and Contingencies - SNIA Environmental Litigation (Details)
1 Months Ended 3 Months Ended 12 Months Ended
Feb. 28, 2022
EUR (€)
Mar. 31, 2026
USD ($)
Mar. 31, 2026
EUR (€)
Dec. 31, 2016
EUR (€)
Mar. 31, 2026
EUR (€)
Dec. 31, 2025
USD ($)
Dec. 31, 2021
EUR (€)
Mar. 31, 2019
EUR (€)
Other Commitments [Line Items]                
Reimbursed legal fees   $ 336,677   € 292,000        
Imposed cost   125,400,000     € 108,800,000      
SNIA environmental liability   389,485,000       $ 396,242,000    
SNIA                
Other Commitments [Line Items]                
Loss contingency, damages awarded and subsequently dismissed   181,300,000 € 157,300,000          
SNIA environmental liability   389,500,000     € 337,800,000      
SNIA | Pending Litigation                
Other Commitments [Line Items]                
Estimate of possible loss   659,600,000            
SNIA | Pending Litigation | SNIA s.p.a                
Other Commitments [Line Items]                
Compensation sought   4,000,000,000.0            
Non-privileged creditor, amount   523,000,000.0            
SNIA | Judicial Ruling                
Other Commitments [Line Items]                
Estimate of possible loss | €             € 453,600,000 € 572,100,000
SNIA | Judicial Ruling | Surety Bond                
Other Commitments [Line Items]                
SNIA litigation guarantee € 270,000,000.0 $ 311,300,000