v3.26.1
Commitments and Contingencies (Tables)
3 Months Ended
Mar. 31, 2026
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Lease, Cost
Below is a summary of the Company’s operating lease right-of-use assets and lease liabilities as of March 31, 2026 and 2025 (in thousands, except for years and %):
March 31,
2026
December 31,
2025
Operating lease right-of-use assets$7,016 $7,639 
Operating lease liability obligations, current$2,303 $2,341 
Operating lease liability obligations, less current portion4,651 5,909 
Total lease liability obligations$6,954 $8,250 
Weighted-average remaining lease term3.33.4
Weighted-average discount rate8.9 %8.9 %
Supplemental cash flow information related to operating leases are as follows (in thousands):
Three Months Ended March 31,
20262025
Cash paid for amounts included in the measurement of lease liabilities$1,328 $378 
Schedule of Lessee, Operating Lease, Liability, Future Minimum Lease Payments
Future minimum lease payments for the Company’s operating lease liabilities as of March 31, 2026 were as follows (in thousands):
2026$1,779 
20272,636 
20282,000 
20291,556 
Total minimum lease payments7,971 
Less: Amount representing interest1,017 
Total lease liability obligations6,954 
Less: Current portion of operating lease liabilities2,303 
Operating lease liabilities, net of current portion$4,651