Regulatory Matters |
6 Months Ended |
|---|---|
Mar. 31, 2026 | |
| Regulatory Assets and Liabilities, Other Disclosure [Abstract] | |
| Regulatory Matters | Regulatory Matters New York Jurisdiction Distribution Corporation's current delivery rates in its New York jurisdiction were approved by the NYPSC in an order issued on December 19, 2024 with rates effective January 1, 2025 (“2024 Rate Order”). The 2024 Rate Order authorizes a three-year rate plan effective October 1, 2024, with a make-whole provision allowing full recovery of revenues that would have been billed at the new rates between October 1, 2024 and December 31, 2024. It also reflects a return on equity of 9.7% and authorized a revenue requirement increase of $57.3 million in fiscal 2025, an additional revenue requirement increase of $15.8 million in fiscal 2026, and an additional revenue requirement increase of $12.7 million in fiscal 2027. These revenue requirement increases are being reflected in customer bills on a levelized basis over the three-year rate plan. The revenue requirement for each year of the three-year plan has been reduced by $14 million for actuarial projections of income that is expected to be recognized for qualified pension and other post-retirement benefits. Qualified pension and other post-retirement benefit income or costs are matched with amounts included in revenue resulting in zero impact to earnings. The 2024 Rate Order approves the continuation of several ratemaking mechanisms, including revenue decoupling and WNA, and establishes a number of new cost trackers and regulatory deferrals. It also includes an earnings sharing mechanism, gas safety and customer service performance metrics (including maintaining the Company’s leak prone pipe replacement program), and provisions that will facilitate achievement of the emissions reduction goals of the CLCPA. Pennsylvania Jurisdiction Distribution Corporation’s current delivery rates in its Pennsylvania jurisdiction were approved by the PaPUC in an order issued on June 15, 2023 with rates effective August 1, 2023 (“2023 Rate Order”). The 2023 Rate Order provided for, among other things, an increase in Distribution Corporation’s annual base rate operating revenues of $23 million and authorized a new weather normalization adjustment mechanism. On January 28, 2026, Distribution Corporation made a filing with the PaPUC seeking an increase in its annual base rate operating revenues of $19.7 million with a proposed effective date of March 29, 2026. The Company is proposing, among other things, a new residential energy efficiency pilot program and to make permanent its weather normalization adjustment mechanism. The Company is also proposing reactivation of the OPEB surcredit (Rider I) to refund $7.2 million for customer bill relief. As reflected in a February 19, 2026 PaPUC Order, the filing was suspended until October 29, 2026 by operation of law unless directed otherwise by the PaPUC. On April 10, 2024, Distribution Corporation filed with the PaPUC a petition for approval of a distribution system improvement charge (“DSIC”) to recover, between base rate cases, capital expenses related to eligible property constructed or installed to rehabilitate, improve and replace portions of the Company’s natural gas distribution system. The DSIC petition was approved by the PaPUC on December 5, 2024 with a cap equivalent to 5% of distribution revenues, and on January 1, 2025, the Company initiated recovery of eligible costs on incremental rate base added after September 30, 2024. During the quarter ended March 31, 2026, Distribution Corporation recovered $2.8 million from customers. The DSIC cap has been met and the Company is unable to earn a return on incremental plant investments. The DSIC will be reset to zero when new base rates become effective as a result of the Company's recent rate filing. FERC Jurisdiction Supply Corporation filed an NGA Section 4 rate case at FERC on April 30, 2026 proposing rate increases to be effective November 1, 2026. Supply Corporation's filing requests an annual cost of service of approximately $404 million, an increase of approximately $95 million from Supply Corporation's settlement of its 2023 rate proceeding. The proposal also includes, among other things, a modernization cost recovery mechanism. On March 17, 2025, FERC approved an amendment to Empire's 2019 rate case settlement, which provides for a modest reduction in Empire’s transportation unit rates, effective November 1, 2025. This settlement amendment is estimated to decrease Empire's revenues on a yearly basis by approximately $0.5 million. Empire will not be able to file a new Section 4 rate case before April 30, 2027 and is required to file a Section 4 rate case by May 31, 2031.
|