v3.26.1
Fixed Assets (Tables)
12 Months Ended
Dec. 31, 2025
Fixed Assets  
Fixed Assets - Vessels, net (Table)

Vessel cost   Accumulated depreciation   Net book value
Balance as at January 1, 2024 $ 1,910,692   $ (85,791)   $ 1,824,901
Vessel acquisitions   1,150,782         1,150,782
Improvements   141         141
Depreciation for the year       (76,454)     (76,454)
Balance as at December 31, 2024 $ 3,061,615   $ (162,245)   $ 2,899,370
Improvements   72         72
Depreciation for the year       (87,065)     (87,065)
Balance as at December 31, 2025 $ 3,061,687   $ (249,310)   $ 2,812,377
Fixed Assets - Vessel acquisitions (Table)

Vessel Delivery Date   Consideration   Debt (Note 8)   Umbrella Seller’s Credit (Note 8)   Advances   Cash
LNG/C Axios II January 2, 2024 $ 314,000 $ 190,000 $ 92,600 $ 31,400 $
LNG/C Assos May 31, 2024   277,000   240,000     27,700   9,300
LNG/C Aktoras June 5, 2024   311,000   240,000   39,900   31,100  
LNG/C Apostolos June 28, 2024   302,000   192,000   2,264   30,200   77,536
Total   $ 1,204,000 $ 862,000 $ 134,764 $ 120,400 $ 86,836

Fixed Assets - Vessel acquisitions 2024 (Table)

Vessels, net $ 1,150,782
Above market acquired charters (Note 7)   58,254
Below market acquired charters (Note 7)   (5,036)
Total $ 1,204,000
Fixed Assets - additional vessels latest technology under construction cost (Table)

         
         
Hull Number/Vessel name CBM   Contract price Expected delivery
LNG/C Amfialos (Hull No.8327) 174,000 $ 248,000 August 2028
LNG/C Amfilochos (Hull No.8328) 174,000   248,000 January 2029
LNG/C Amissos (Hull No.8329) 174,000   248,000 February 2029
Fixed Assets - vessels under construction cost (Table)

    Vessels under construction cost
Balance as at January 1, 2024 $ 140,369
Advances and initial expenses for vessels under construction   249,921
Balance as at December 31, 2024 $ 390,290
Advances and initial expenses for vessels under construction   314,111
Balance as at December 31, 2025 $ 704,401
Fixed Assets - Advances for vessels under construction - related party (Table)

    Advances for vessels under construction-related party
Balance as at January 1, 2024 $ 174,400
Transfer to vessels, net   (120,400)
Balance as at December 31, 2024 $ 54,000
  -
Balance as at December 31, 2025 $ 54,000