v3.26.1
Provision for de-characterization of dam structures and asset retirement obligations (Details 1)
$ in Millions
12 Months Ended
Dec. 31, 2025
USD ($)
IfrsStatementLineItems [Line Items]  
Balance at the beginning $ 5,763
Revision to estimates - amounts for closed plants charged to the income statement 13
Revision to estimates - capitalized amounts for operating plants 214
Disbursements (711)
Monetary and present value adjustments 327
Acquisition of Alianca Energia (24)
Translation adjustment 580
Balance at the end 6,162
Decharacterization Of Upstream Geotechnical Structures [Member]  
IfrsStatementLineItems [Line Items]  
Balance at the beginning 2,213
Revision to estimates - amounts for closed plants charged to the income statement (185)
Revision to estimates - capitalized amounts for operating plants
Disbursements (378)
Monetary and present value adjustments 171
Acquisition of Alianca Energia
Translation adjustment 276
Balance at the end 2,097
Provision for decommissioning, restoration and rehabilitation costs [member]  
IfrsStatementLineItems [Line Items]  
Balance at the beginning 3,106
Revision to estimates - amounts for closed plants charged to the income statement 173
Revision to estimates - capitalized amounts for operating plants 170
Disbursements (218)
Monetary and present value adjustments 134
Acquisition of Alianca Energia (2)
Translation adjustment 258
Balance at the end 3,621
Other environment related provision [member]  
IfrsStatementLineItems [Line Items]  
Balance at the beginning 444
Revision to estimates - amounts for closed plants charged to the income statement 25
Revision to estimates - capitalized amounts for operating plants 44
Disbursements (115)
Monetary and present value adjustments 22
Acquisition of Alianca Energia (22)
Translation adjustment 46
Balance at the end $ 444