v3.26.1
Commitments and Contingencies - Narrative (Details)
$ in Millions
12 Months Ended
Dec. 12, 2025
USD ($)
Dec. 01, 2025
USD ($)
Apr. 12, 2023
claim
Mar. 17, 2018
USD ($)
Nov. 28, 2016
mi
Dec. 31, 2025
USD ($)
Jun. 11, 2024
USD ($)
City LYNX Gold Line Phase 2 Streetcar              
Commitments and Contingencies              
Original length of streetcar system constructed | mi         1.5    
Increase in length of streetcar system, previously constructed | mi         2.5    
City of Charlotte | Pending Litigation              
Commitments and Contingencies              
Number of claims | claim     10        
City of Charlotte | Pending Litigation | Minimum              
Commitments and Contingencies              
Damages sought             $ 115.0
CLJV | Washington State Convention Center Project              
Commitments and Contingencies              
Construction contract price       $ 81.4      
Contract claim value       80.0      
Contract asset from claims       40.3      
Construction contract, Retainage receivable       6.4      
Loss Contingency Accrual       $ 58.0      
Litigation settlement, amount awarded to other party   $ 57.1          
Sanctions order awarded to other party $ 4.8            
Non-cash charge to revenue   40.3          
Non-cash reduction to contract assets   40.3          
Long term accrued liability   89.1       $ 89.1  
Decrease in retainage receivables   6.4       6.4  
Decrease in revenue   46.7       6.4  
Cost of construction   89.1          
Total impact to consolidated statement of operations   $ 135.8          
Increase in cost of construction           $ 89.1