Summary of Significant Accounting Policies - Washington State Convention Center Project (Details) - Washington State Convention Center Project - CLJV - USD ($)
$ in Millions
12 Months Ended
Dec. 01, 2025
Dec. 31, 2025
Commitments and Contingencies    
Litigation Settlement, Amount Awarded to Other Party $ 57.1  
Non-cash charge to revenue 40.3  
Decrease in revenue 46.7 $ 6.4
Long term accrued liability 89.1 89.1
Decrease in retainage receivables 6.4 6.4
Increase in cost of construction   $ 89.1
Total impact to consolidated statement of operations 135.8  
Cost of construction 89.1  
Non-cash reduction to contract assets $ 40.3