v3.26.1
Note 16 - Broadband Grants (Details Textual) - USD ($)
Mar. 05, 2024
Nov. 21, 2023
Dec. 08, 2022
Aug. 30, 2022
Dec. 31, 2025
United States Low-Density Broadband Grant [Member]          
Government Assistance, Percentage of Total Cost to Build Fiber Connections Awarded       75.00%  
Government Contract Receivable       $ 3,210,000  
Total Project Costs       $ 4,280,000  
Government Assistance, Percentage of Total Cost of Building Fiber Connections Matched By Company       25.00%  
Government Contract Receivable, Progress Payment Offset         $ 0
Goodhue County Minnesota Low-Density Broadband [Member]          
Government Contract Receivable, Progress Payment Offset         0
Government Assistance, Total Cost to Build Fiber Connections Awarded   $ 277,733      
Minnesota DEED Low-Density Broadband Grant [Member]          
Government Assistance, Percentage of Total Cost to Build Fiber Connections Awarded 75.00%        
Government Contract Receivable $ 1,884,429        
Total Project Costs $ 2,512,572        
Government Assistance, Percentage of Total Cost of Building Fiber Connections Matched By Company 25.00%        
Government Contract Receivable, Progress Payment Offset         107,837
December 2022 DEED Broadband Grants [Member]          
Government Contract Receivable     $ 8,594,688    
Total Project Costs     $ 18,139,749    
Government Contract Receivable, Progress Payment Offset         $ 8,594,688
December 2022 DEED Broadband Grants [Member] | Minimum [Member]          
Government Assistance, Percentage of Total Cost to Build Fiber Connections Awarded     45.00%    
Government Assistance, Percentage of Total Cost of Building Fiber Connections Matched By Company     50.00%    
December 2022 DEED Broadband Grants [Member] | Maximum [Member]          
Government Assistance, Percentage of Total Cost to Build Fiber Connections Awarded     50.00%    
Government Assistance, Percentage of Total Cost of Building Fiber Connections Matched By Company     55.00%