Schedule of Plant Asset Consists (Details) - USD ($) |
Dec. 31, 2025 |
Dec. 31, 2024 |
|---|---|---|
| Process Plant | ||
| Mill purchase, detailed engineering, and construction costs | $ 94,026,121 | $ 65,545,594 |
| Capitalized interest (note 10) | 4,155,884 | 1,848,473 |
| Disposal of Grinding Circuits | (984,820) | (984,820) |
| Process Plant | $ 97,197,185 | $ 66,409,247 |