13)       Commitments and Contingencies
 
Since the Company uses the liquidation basis of accounting, the Company has accrued estimated liquidation costs to the extent they are known and are reasonably determinable, which includes the items discussed in this footnote.
 
Office Lease
 
The Company has a lease for office space which expires on May 31, 2026. The monthly rent is approximately $1,600.
 
Employment Agreements
 
The Wind-Down Entity has part-time employment agreements with its two executive officers which renew automatically on an annual basis, subject to the right of either party to terminate the agreement at any time and for any reason on thirty days’ advance written notice.
 
Construction Defect Claim
 
In June 2023, the owner of a single-family home sold by the Development Entity for approximately $60 million asserted a construction defect claim against the Development Entity. The claim currently alleges soils-related damage to retaining walls, the pool, indoor and outdoor flooring, among other things, and other damage resulting from water leaks. The Development Entity’s engineering consultants have been evaluating a multi-phase repair plan to address the situation.
 
The recommended scope of work for the initial phase includes the repair and remediation of a retaining wall. On August 7, 2024, the Development Entity submitted a building permit application to the Los Angeles Department of Building and Safety for the retaining wall repair. The building permit for the initial repair was issued on October 30, 2025 and the construction contract for the initial repairs was signed. As of December 31, 2025, the initial repair phase had not begun. Based on current information, the initial phase is expected to take three to six months to complete. Once the initial retaining wall repair is completed, the retaining wall and site will need to be monitored for a period of time. After this monitoring is completed and the results are evaluated, the Development Entity expects that the second phase and further monitoring will begin.
 
The Development Entity’s consultants and engineers are evaluating the scope of repairs that will be needed after the retaining wall is repaired. Engineering studies, site soils analyses and site monitoring are in process, the results of which are expected to help define the required additional scope of work. Thus far, certain repairs have been identified to repair the pool, pool deck and cracks in the interior ceilings and floors. Additional repairs may be identified based on the results of additional testing and site evaluation and after the retaining wall is repaired.
 
In addition, there have been other construction defect claims that have required immediate repair. In October 2024, the Development Entity was notified about a potential leak in the pool that was causing water levels to decrease more rapidly than usual. A leak specialist was retained to test and identify the leak location and underground pipes were replaced. In February 2025, the Development Entity was made aware of potential damage resulting from water leaks and seepage in the garage and other areas of the home. In response, the Development Entity retained consultants to assist with the evaluation of the causes of the situation and to determine appropriate remediation measures. In March 2025, the Development Entity was informed that another glass pane had broken at the property due to ongoing movement on the site. The Development Entity has completed some repairs in response to these claims, but until the initial repair of the retaining wall and monitoring activities are completed, the Development Entity will be unable to complete all necessary repairs. In addition, the Development Entity is unable to determine whether these damages resulted from the same underlying issues currently being addressed. See Note 14 for additional information.
Based on current information available to it, the Development Entity believes that the repairs to address the construction defect claims can be completed by February 15, 2027; however, it may take longer based on the results of the initial phase of repair, subsequent monitoring and the scope of additional repairs that may be required, as well as unforseen delays in construction.
 
As of December 31, 2025, there was approximately $8,061,000 accrued for estimated costs related to the construction defect claim asserted against the Development Entity. The estimated costs are the Development Entity’s best estimate at this time and are subject to change as additional information becomes available. As the results of the initial phase of repair and information from the related monitoring become available and the planning for the subsequent phases is finalized, additional costs may need to be accrued. The amount of the Development Entity’s ultimate exposure for the construction defect claim is currently unknown and may be materially different from the amount that has been accrued as of December 31, 2025 in the Company’s consolidated financial statements (see Note 5 for additional information). The Development Entity reviews these estimates on a quarterly basis and accrues updated cost estimates as appropriate.
 
Construction Defect Insurance
 
The Company believes that all or a portion of the costs related to the construction defect claim may ultimately be borne by third parties, including the Development Entity’s insurers, as described below.
 
The Development Entity purchased primary and two excess coverage insurance policies covering certain risks arising out of the Development Entity’s development of the single-family home which is the subject of the construction defect claim. The Development Entity tendered the claim to its primary and excess layer insurers on June 28, 2023. The insurer that issued the primary and first excess layer coverage agreed to defend the Development Entity subject to a reservation of rights. As of December 31, 2025, this insurer has advanced the Development Entity approximately $5,852,000 for the estimated cost of the initial repair phase and some, but not all of the out-of-pocket costs incurred by the Development Entity which it asserts are covered by the primary and first excess layer policies. The funds advanced by this insurer are included in cash, cash equivalents and short-term investments and have not been netted against accrued development costs in the Company’s consolidated financial statements.
 
As of December 31, 2025, the Development Entity has exhausted its primary and first excess layer coverage and has tendered its claim to the second excess layer insurer. At this time, the second excess layer insurer has agreed to defend the Development Entity subject to a reservation of rights.
 
Litigation
 
Prior to the receipt of any reimbursements and advance payments, on August 9, 2024, the Development Entity filed a lawsuit against its primary and two excess layer insurers demanding that they defend and indemnify it against the construction defect claim. The lawsuit seeks, among other relief, damages from the primary and two excess layer insurers for amounts the Development Entity has incurred, and may incur, in connection with the investigation and repair of the construction defect claim, as well as declaratory relief against the primary and excess layer insurers. On August 20, 2024, the lawsuit against the insurers was stayed until October 21, 2024. On October 15, 2024, the Development Entity agreed to extend the stay by an additional three months, until January 29, 2025, during which time the parties agreed to seek informal resolution of the dispute. On October 24, 2024, the Development Entity dismissed its claim against the second excess layer insurance carrier without prejudice and subject to a tolling agreement. On January 27, 2025, the primary and first excess layer insurer approved coverage for the initial repair phase. The case against the primary and first excess layer insurer is currently stayed until the initial case management conference, which was scheduled to occur on October 30, 2025. On October 30, 2025, the Development Entity agreed to extend the stay in the case against the primary and first excess layer insurer by an additional three months, until January 26, 2026. See Note 14 for additional information. The Trust may add the second excess layer insurer to the litigation if the second excess layer insurer refuses to provide coverage after the primary and first excess layer policy is exhausted. 
Additionally, on May 28, 2024, the Development Entity filed a lawsuit against 13 different parties, including the prior owner, contractors, G3, and other professionals involved in the development of the site and the construction of the home. G3 is a construction firm specializing in the development of high-end luxury residences. G3 is owned by Terry Goebel, who was a member of the Supervisory Board until his resignation on March 5, 2024, and his son Terry Goebel. The lawsuit seeks, among other relief, contribution from these parties for the costs that the Development Entity has incurred, and may incur, in connection with the investigation and repair of the construction defect claim. Based on further investigation after filing of the complaint, the Development Entity dismissed three defendants without prejudice. A mediation was held on February 20, 2025, which did not result in a settlement. The parties agreed to allow each other time to gather and exchange information, as needed. A subsequent mediation date has not been scheduled. This litigation is in its preliminary stages, and the Company cannot predict whether the Development Entity will be successful in recovering the costs incurred to date and further costs incurred to address the construction defect claim from these parties.
 
The Company has accrued legal and professional costs related to pursuing the aforementioned litigation. Actual costs incurred may exceed the amount accrued as of December 31, 2025. The Development Entity reviews these estimates on a quarterly basis and accrues updated cost estimates as appropriate.
 
The Company is not presently the defendant in any material litigation nor, to the Company’s knowledge, is any material litigation threatened against the Company other than as described herein.