Closure and rehabilitation provisions |
12 Months Ended | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Jun. 30, 2025 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Text block 1 [Abstract] | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Closure and rehabilitation provisions | 15 Closure and rehabilitation provisions
Profile of closure and rehabilitation cash flows The table below indicates the estimated profile of the Group’s closure and rehabilitation provisions. The profile reflects the undiscounted forecast cash flows that underpin the provisions. In some instances, the Group has an obligation to rehabilitate and maintain a closed site for an indefinite period. For the purpose of this analysis, the cashflow period has been restricted to 100 years.
The Group is required to close and rehabilitate sites and associated facilities at the end of or, in some cases, during the course of production to a condition acceptable to the relevant authorities, as specified in licence requirements and the Group’s closure performance requirements . The key components of closure and rehabilitation activities are:
Recognition and measurement Provisions for closure and rehabilitation are recognised by the Group when:
Closed sites Where future economic benefits are no longer expected to be derived through operation, changes to the associated closure and remediation costs are charged to the income statement in the period identified. The amount charged to the income statement, inclusive of exchange translation and remediation costs related to contaminated sites, was US$101 million in the year ended 30 June 2025 (2024: US$38 million; 2023: US$4 million). Key es ti mates Closure cost estimates are generally based on conceptual level studies early in the operating life of an asset with more detailed studies and planning performed as closure risks (including those related to climate change) are identified and/or as an asset, or parts thereof, near closure. As such, the recognition and measurement of closure and rehabilitation provisions requires the use of significant estimates and assumptions, including, but not limited to:
The extent, cost and timing of future closure activities may also be impacted by the potential physical impacts of climate change and the transition to a low-carbon economy. Further detail is provided in note 16 ‘Climate change’. Estimates for post-closure monitoring and maintenance reflect the Group’s strategies for individual sites, which may include possible relinquishment. The period of monitoring and maintenance included in the provision requires judgement and considers regulatory and licencing requirements, the outcomes of studies and management’s current assessment of stakeholder expectations. While progressive closure is performed across a number of operations, significant activities are generally undertaken at the end of the production life at the individual sites, the estimated timing of which is informed by the Group’s current assumptions relating to demand for commodities and carbon pricing, and their impact on the Group’s long-term price forecasts. Approximately 44 per cent (2024: 52 per cent) of the Group’s total undiscounted forecast cashflows are expected to be incurred after more than 30 years, reflecting the long-lived nature of many of the Group’s operations which have remaining production lives ranging from 4-86 years (2024: 5-87 years). The discount rates applied to the Group’s closure and rehabilitation provisions are determined by reference to the currency of the closure cash flows, the period over which the cash flows will be incurred and prevailing market interest rates (where available). The discount rates applied to the Group’s closure and rehabilitation provisions were revised during the year to reflect increases in market interest rates. The effect of changes to discount rates was a decrease of approximatively US$340 million in the closure and rehabilitation provision of which US$110 million in respect of closed and contaminated sites was recognised in the income statement. While the closure and rehabilitation provisions reflect management’s best estimates based on current knowledge and information, further studies, trials and detailed analysis of relevant knowledge and resultant closure activities for individual assets continue to be performed throughout the life of asset. Such studies and analysis can impact the estimated costs of closure activities. Estimates can also be impacted by the emergence of new closure and rehabilitation techniques, changes in regulatory requirements and stakeholder expectations for closure (including costs associated with equitable transition), development of new technologies, risks relating to climate change and the transition to a low-carbon economy, and experience at other operations. These uncertainties may result in future actual expenditure differing from the amounts currently provided for in the balance sheet. Sensitivity A 0.5 per cent increase in the discount rates applied at 30 June 2025 would result in a decrease to the closure and rehabilitation provision of approximately US$665 million, a decrease in property, plant and equipment of approximately US$443 million in relation to operating sites and an income statement credit of approximately US$222 million in respect of closed and contaminated sites. In addition, the change would result in a decrease of approximately US$27 million to depreciation expense and a US$29 million increment in net finance costs due to unwind of discount for the year ending 30 June 2026. Given the long-lived nature of the majority of the Group’s assets, the majority of final closure activities are generally not expected to occur for a significant period of time. However, a one-year acceleration in forecast cash flows of the Group’s closure and rehabilitation provisions, in isolation, would result in an increase to the provision of approximately US$291 million, an increase in property, plant and equipment of US$169 million in relation to operating sites and an income statement charge of US$122 million in respect of closed sites and contaminated sites. |