v3.25.2
Regulatory - Additional Information (Detail)
$ in Millions
6 Months Ended 12 Months Ended
Jan. 31, 2027
USD ($)
Jan. 31, 2026
USD ($)
Feb. 04, 2025
USD ($)
Jan. 31, 2025
USD ($)
Dec. 03, 2024
Oct. 09, 2024
Customer
Jun. 30, 2025
USD ($)
Dec. 31, 2024
USD ($)
Sep. 26, 2024
Customer
Public Utilities General Disclosures [Line Items]                  
Intervening party description             On March 3, 2025, two intervening parties each filed a notice of appeal to the Florida Supreme Court regarding the outcome of Tampa Electric's 2024 base rate proceeding. As of August 8, 2025, the intervening parties have not filed their briefs related to the appeal    
Accumulated depreciation             $ 3,516 $ 3,348  
Storm restoration preparation costs             285 377  
Regulatory asset for storm restoration costs             $ 1,376 $ 1,441  
Settlement Agreement [Member]                  
Public Utilities General Disclosures [Line Items]                  
Allowed equity in the capital structure         54.00%        
Minimum [Member] | Settlement Agreement [Member]                  
Public Utilities General Disclosures [Line Items]                  
Percentage of ROE       9.50%          
Maximum [Member] | Settlement Agreement [Member]                  
Public Utilities General Disclosures [Line Items]                  
Percentage of ROE       11.50%          
Mid Point [Member] | Settlement Agreement [Member]                  
Public Utilities General Disclosures [Line Items]                  
Percentage of ROE       10.50%          
Storm Restoration Cost Recovery [Member]                  
Public Utilities General Disclosures [Line Items]                  
Minimum cost recovery period             12 months    
Replenishment reserve for recovery of cost             $ 56    
Tampa Electric Base Rates, on April 02, 2024 [Member]                  
Public Utilities General Disclosures [Line Items]                  
Effect of base rate adjustment on revenue       $ 297          
Tampa Electric Base Rates, on April 02, 2024 [Member] | Scenario Forecast [Member]                  
Public Utilities General Disclosures [Line Items]                  
Effect of base rate adjustment on revenue $ 72 $ 100              
Tampa Electric Base Rates on August 22, 2024 [Member] | After FPSC Final Order [Member]                  
Public Utilities General Disclosures [Line Items]                  
Effect of base rate adjustment on revenue       $ 185          
Tampa Electric Base Rates on August 22, 2024 [Member] | After FPSC Final Order [Member] | Scenario Forecast [Member]                  
Public Utilities General Disclosures [Line Items]                  
Effect of base rate adjustment on revenue $ 9 $ 87              
Hurricane Helene [Member]                  
Public Utilities General Disclosures [Line Items]                  
Storm restoration costs charged to reserve             48    
Number of customers impacted by storm | Customer                 100,000
Hurricane Milton [Member]                  
Public Utilities General Disclosures [Line Items]                  
Storm restoration costs charged to reserve             340    
Number of customers impacted by storm | Customer           600,000      
Number of years worst weather event impact on area           100 years      
Hurricane Idalia Debby Helene and Milton [Member]                  
Public Utilities General Disclosures [Line Items]                  
Storm restoration costs     $ 466       $ 98