Nuclear Decommissioning Nuclear Decommissioning
Nuclear Decommissioning Asset Retirement Obligations
We have a legal obligation to decommission our nuclear power plants following the permanent cessation of operations. See Note 10 — Asset Retirement Obligations of our 2024 Form 10-K for additional information regarding AROs and the financial statement impact of changes in estimates.
The following table provides a rollforward of the nuclear decommissioning AROs reflected in the Consolidated Balance Sheets from December 31, 2024 to June 30, 2025:
Balance as of December 31, 2024
$12,186 
Accretion expense309 
Net decrease due to changes in, and timing of, estimated future cash flows
(76)
Costs incurred related to decommissioning plants(8)
Balance as of June 30, 2025
$12,411 
NDT Funds
We had NDT funds totaling $18,329 million and $17,321 million as of June 30, 2025 and December 31, 2024, respectively. The current portions of the NDT funds, which are included in Other current assets in our Consolidated Balance Sheets, were not material as of June 30, 2025 and December 31, 2024. See Note 16 — Supplemental Financial Information for additional information on activities of the NDT funds.
Accounting Implications of the Regulatory Agreement Units
See Note 1 — Basis of Presentation and Note 10 — Asset Retirement Obligations of our 2024 Form 10-K for additional information on the Regulatory Agreement Units.
The following table presents our noncurrent payables to ComEd, PECO, CenterPoint, and AEP Texas reflected as Payables related to Regulatory Agreement Units in the Consolidated Balance Sheets as of June 30, 2025 and December 31, 2024:
June 30, 2025December 31, 2024
ComEd$4,032 $3,780 
PECO379 247 
CenterPoint
392 365 
AEP Texas
136 126 
Payables related to Regulatory Agreement Units$4,939 $4,518 
NRC Minimum Funding Requirements
NRC regulations require that licensees of nuclear generating facilities demonstrate reasonable assurance that funds will be available in specified minimum amounts for radiological decommissioning of the facility at the end of its life.
We filed our biennial decommissioning funding status report with the NRC in March 2025 for all units, including our shutdown units, except for STP units which were included in a separate report to the NRC submitted by STPNOC. The status reports demonstrated adequate decommissioning funding assurance based on trust fund values as of December 31, 2024 for all our units except for Peach Bottom Unit 1. Financial assurance for decommissioning Peach Bottom Unit 1 is provided by collections from PECO customers. See Note 10 — Asset Retirement Obligations of our 2024 Form 10-K for additional information.