Commitments and Contingencies
Note 5. Commitments and Contingencies
Saluggia Site Hazardous Substances
LSM, formerly a subsidiary of Sorin, one of the companies that merged into LivaNova PLC in 2015, manages site services for the campus in Saluggia, Italy. In addition to being a former LivaNova manufacturing facility, the Saluggia campus is also the location of manufacturing facilities of third parties, a cafeteria for workers, and storage facilities for hazardous substances and equipment previously used in a nuclear research center, later turned nuclear medicine business, between the 1960s and the late 1990s. Pursuant to authorization from the Italian government, LSM performs ordinary maintenance, secures the facilities, monitors air and water quality, and files applicable reports with the competent environmental authorities.
In 2020, LSM received correspondence from ISIN requesting that, within five years, LSM demonstrate the financial capacity to meet its obligations under Italian law to clean and dismantle any contaminated buildings and equipment, as well as to deliver hazardous substances to a national repository. The national repository will be built by the Italian government at a location and time yet to be determined. ISIN subsequently published Technical Guide n. 30, which identifies the technical criteria and general safety and protection requirements for the design, construction, operation, and dismantling of temporary storage facilities for the hazardous substances.
Although there is no legal obligation to deliver any hazardous substances, as the performance of these obligations is contingent on the construction of the as-yet unbuilt national repository, based on the aforementioned factors, the Company concluded its obligation to clean, dismantle, and deliver any hazardous substances to a national repository is probable and reasonably estimable. The estimated liability as of June 30, 2025 was $40.4 million (€34.5 million), which represented the estimated low end of the range of loss, with an estimated maximum end of the range of loss of $55.3 million (€47.2 million). The estimated liability as of December 31, 2024 was $36.7 million (€35.4 million).
SNIA Environmental Litigation
Sorin was created as a result of a spin-off from SNIA in 2004, and in 2015, Sorin was merged into LivaNova. SNIA subsequently became insolvent, and the Public Administrations sought compensation from SNIA in an aggregate amount of approximately $4.0 billion for remediation costs relating to the environmental damage at chemical sites previously operated by SNIA’s other subsidiaries.
There are proceedings relating to the SNIA bankruptcy to which LivaNova is not a party in the Bankruptcy Court of Udine and the Bankruptcy Court of Milan. In 2011, the Bankruptcy Court of Udine held that the Public Administrations were not creditors of either SNIA or its subsidiaries in connection with their claims in the Italian insolvency proceedings. The Public Administrations appealed. In 2016, the Court of Udine rejected the appeal, and the Public Administrations appealed to the Italian Supreme Court. Similarly, in 2014, the Bankruptcy Court of Milan held that the Public Administrations were not creditors of either SNIA or its subsidiaries. The Public Administrations appealed. In April 2022, the Bankruptcy Court of Milan declared the Public Administrations to be a non-privileged creditor of SNIA for up to €453.6 million ($531.4 million as of June 30, 2025), and the Public Administrations appealed to the Italian Supreme Court.
In 2012, SNIA filed a civil action against Sorin in the Civil Court of Milan asserting joint liability of a parent and a spun-off company; the Public Administrations entered voluntarily into the proceeding, asking Sorin, as jointly liable with SNIA, to pay compensation for SNIA’s environmental damages. In 2016, the Court of Milan dismissed all legal actions of SNIA and of the Public Administrations further requiring the Public Administrations to pay Sorin €292,000 ($342,109 as of June 30, 2025) for legal fees. The Public Administrations appealed the 2016 Decision to the Court of Appeal. On March 5, 2019, the Court of Appeal issued a partial decision on the merits declaring Sorin/LivaNova jointly liable with SNIA for SNIA’s environmental liabilities in an amount up to the fair value of the net worth received by Sorin because of the spin-off of Sorin from SNIA in 2004, an estimated €572.1 million ($670.3 million as of June 30, 2025). LivaNova appealed the partial decision on liability to the Italian Supreme Court in August 2019.
In 2021, the Court of Appeal delivered the remainder of its decision, ordering LivaNova to pay damages of €453.6 million ($531.4 million as of June 30, 2025). LivaNova appealed the decision on damages in December 2021. On February 21, 2022, the Court of Appeal notified the Company that it granted the Company a suspension with respect to the payment of damages until a decision was reached on the appeal to the Italian Supreme Court. This suspension was subject to LivaNova providing a first demand bank guarantee of €270.0 million ($316.3 million as of June 30, 2025) within 30 calendar days, and on March 21, 2022, LivaNova delivered the SNIA Litigation Guarantee, thereby satisfying the condition.
In 2022, in response to one of a number of appeals asserted by LivaNova, the Italian Supreme Court issued an ordinance, a procedural document, whereby the Italian Supreme Court referred a question on the interpretation of a European directive on demergers to the ECJ. Specifically, the ordinance asked the ECJ to provide a binding decision as to whether a company resulting from a demerger can be held jointly and severally liable not only for the established liabilities of the demerged company that were articulated at the time of demerger, but also for the environmental liabilities of the demerged company that materialized after the demerger which are derived from actions performed prior to the demerger. On July 29, 2024, the ECJ issued a judgment in response to the ordinance. The ECJ judgment states that a demerged company can be held responsible for liabilities not established prior to a demerger as long as the liabilities derive from the conduct of a demerged company prior to the demerger. The ECJ judgment also states that national law should determine whether liability for damages stemming from conduct after a demerger can be assigned to a demerged company.
On March 14, 2025, the Italian Supreme Court issued its decision in response to all of the appeals of the Company and counter-appeals submitted by the Public Administrations. The Italian Supreme Court determined that LivaNova can be held jointly and severally liable for the established liabilities of SNIA at the time of demerger, as well as the environmental liabilities of the demerged company that materialized after the demerger, which are derived from actions performed prior to the demerger; however, the Italian Supreme Court also ruled that the Company should not be held responsible for certain payments previously approved by the Court of Appeal in the amount of €157.3 million ($184.3 million as of June 30, 2025). The case has been referred back to the Court of Appeal to implement the decisions respecting costs and damages in accordance with the judgment of the Italian Supreme Court.
As a result of the decision by the Italian Supreme Court, the Company recorded a current liability in the first quarter of 2025 and has continued to accrue interest on the liability since that time. As of June 30, 2025, the Company has a current liability of €334.8 million ($392.3 million) on the condensed consolidated balance sheet, representing its best estimate of the liability, inclusive of estimated costs, fees, interest, and taxes. These estimated costs do not include the Company’s legal fees, which are expensed as incurred and included in SG&A in LivaNova’s condensed consolidated statements of income (loss). The Company has determined that it has sufficient resources to cover the liability as of June 30, 2025.
On March 31, 2025, as a result of the decision by the Italian Supreme Court, the SNIA Litigation Guarantee was terminated, and the restriction on the cash deposit held as collateral was released. For additional information on the financing of the guarantee, refer to “Note 11. Supplemental Financial Information.”
On May 15, 2025, as a procedural step outlined above, the Ministry served the Company with a filing to return the proceedings to the Court of Appeal. In addition to seeking return of the case to the Court of Appeal, the Ministry asserted that the Court of Appeal forego an examination of the amounts disapproved by the Italian Supreme Court and instead impose costs of approximately €108.8 million at a minimum. These assertions are counter to the decision of the Italian Supreme Court’s judgment, which disapproved costs of €157.3 million ($184.3 million as of June 30, 2025). The Ministry’s filing is not a legal judgment or demand for payment. The Company disagrees with the assertions made in the Ministry’s filing and believes they contradict the decisions of the Italian Supreme Court. The Company intends to challenge the Ministry’s assertions and purported costs and to defend its position in accordance with the Italian Supreme Court’s judgment. The Company continues to believe that its recorded liability remains the best estimate of the liability associated with the SNIA matter, and, as such, no adjustments were made to the accrual in response to the filing on May 15, 2025. A hearing has been scheduled for January 28, 2026.
Product Liability Litigation
The Company continues to be involved in litigation involving LivaNova’s 3T device. The litigation includes the cases remaining in the MDL, various U.S. state court cases, and claims in jurisdictions outside the United States. As of August 6, 2025, the Company was aware of approximately 60 filed and unfiled claims worldwide. The complaints generally seek damages and other relief based on theories of strict liability, negligence, breach of express and implied warranties, failure to warn, design and manufacturing defect, fraudulent and negligent misrepresentation or concealment, unjust enrichment, and violations of various state consumer protection statutes.
For the three and six months ended June 30, 2025, LivaNova recorded an additional liability of $0.1 million and $0.6 million, respectively, upon receiving new information regarding the nature of certain claims. As of June 30, 2025 and December 31, 2024, the provision for these matters was $15.4 million and $15.8 million, respectively. While the amount accrued represents LivaNova’s best estimate for those worldwide filed and unfiled claims of which LivaNova is aware and believes are both probable and estimable at this time, the actual liability for resolution of these matters may vary from the Company’s provision. A provision has not been recorded for any claims where a potential loss is not determined to be probable, or a potential loss or range of potential loss is not reasonably estimable at this time.
The following table presents the changes in the litigation provision liability for the six months ended June 30, 2025 (in thousands):
As of December 31, 2024
$15,843 
Payments(1,932)
Adjustments (1)
629 
FX and other904 
As of June 30, 202515,444 
Less: Current portion as of June 30, 202512,171 
Long-term portion as of June 30, 2025 (2)
$3,273 
(1)Adjustments to the litigation provision are included in other operating expenses on the condensed consolidated statements of income (loss).
(2)Included in other long-term liabilities on the condensed consolidated balance sheets.
Italian MedTech Payback Measure
In 2015, the Italian Parliament introduced a law regarding public contracts with the National Healthcare System for the supply of goods and services. In particular, the law introduced a payback measure requiring companies selling medical devices in Italy to repay a percentage of the healthcare expenditures exceeding the regional maximum caps for medical devices. In August 2022, a decree was published which provided guidance and timetables for the payback measure. In response, LivaNova filed an appeal at the Administrative Court against the decree of the Ministry of Health, assessing the amount payable and against the payback law. LivaNova also filed appeals against the regions requesting payments. In August 2023, the Administrative Court upheld LivaNova’s request to suspend the effect of the requests for payment by the regions, pending the decision by the Administrative Court on the merits of the case. In November 2023, the Administrative Court, in a separate matter, asked the Constitutional Court whether the payback law was compliant with the Italian Constitution and pending the decision by the Constitutional Court, all cases brought by medical device companies in this matter were suspended. On July 22, 2024, the Constitutional Court determined that the payback law is compliant with the Italian Constitution and that companies may reduce their payment obligations between 2015-2018 to 48% of the amount originally charged to companies. On June 30, 2025, the Italian Government introduced a decree that, if converted to law, would allow companies to settle their 2015-2018 payment obligations by paying 25% of the originally requested amounts if those companies were to withdraw any outstanding appeals related to that period and remit payment within 30 days of the law entering into force. The Company is evaluating the decree, which is expected to become effective during the third quarter of 2025. Based on market and product information and the 48% ruling by the Constitutional Court, the amount reserved for this matter was $19.7 million and $16.0 million as of June 30, 2025 and December 31, 2024, respectively, and is included in accrued liabilities and other in the condensed consolidated balance sheets. However, the actual liability could vary. Amounts recognized associated with the Italian MedTech payback measure are recorded as a reduction to net revenue in the condensed consolidated statements of income (loss).
Cyber Litigation
In connection with the cybersecurity incident initially reported on November 20, 2023, LivaNova USA was named as a defendant in six putative class action lawsuits filed in the United States District Court for the Southern District of Texas in June
and July 2024. Those cases were consolidated in a single action, and the plaintiffs filed against LivaNova USA a consolidated class action complaint, which asserted claims of negligence, breach of contract, and violation of various state consumer protection laws. The plaintiffs sought damages, equitable/injunctive relief, and attorney’s fees, costs, and expenses, among other relief. The parties entered into mediation and agreed to a class action settlement, with respect to which the Company recorded an accrual of $1.2 million for the quarter ended September 30, 2024. The class action settlement received approval from the court on April 4, 2025 and is now final. The Company expects all settlement administration activities to be completed in 2025.
In addition, HHS’s Office for Civil Rights is investigating the incident pursuant to its authority to enforce the HIPAA rules regarding privacy, security, and breach notification. The Office for Civil Rights issued a request for information regarding the Company’s response to the incident and the Company’s compliance with HIPAA rules, to which the Company responded. The Office for Civil Rights may issue additional requests for information and documentation. In connection with its investigation, the Office for Civil Rights may, among other measures, seek to impose civil monetary penalties against LivaNova and seek to require that the Company implement a corrective action plan. Furthermore, the Company has received, and may receive in the future, additional government requests for information about the incident, to which LivaNova will respond. For example, the Italian data protection authority recently requested that LivaNova provide certain information regarding the incident, and the Company responded to the request.
Other Matters
Additionally, LivaNova is the subject of various pending or threatened legal actions and proceedings that arise in the ordinary course of LivaNova’s business. These matters are subject to many uncertainties and outcomes that are not predictable and that may not be known for extended periods of time. Since the outcome of these matters cannot be predicted with certainty, the costs associated with them could have a material adverse effect on LivaNova’s consolidated results of operations, financial position, or liquidity.