v3.25.2
SUBSEQUENT EVENTS
3 Months Ended
Jun. 30, 2025
Subsequent Events [Abstract]  
SUBSEQUENT EVENTS

NOTE 19 — SUBSEQUENT EVENTS

On June 23, 2025, we entered into the Term Sheet with respect to our remaining earn-out obligations owed to Final Frontier pursuant to the Voltrek Acquisition, and on July 31, 2025, we entered into the Term Sheet Amendment. Pursuant to the Term Sheet Amendment, we agreed to pay Final Frontier the previously agreed upon $875,000 payment in full and final payment of our fiscal 2024 Voltrek Acquisition earn-out obligation as follows: $500,000 was paid on August 1, 2025 and the remaining $375,000 will be paid on September 3, 2025.

On August 4, 2025, we received a letter from Final Frontier disagreeing with our calculation of the Voltrek Acquisition earn out payment for fiscal 2025 and the cumulative Voltrek Acquisition earn out payment for the three-year period ended March 31, 2025. We are in the process of assessing the letter.